Streets
39th Street Roadway Reconstruction
Project Summary
This project involves roadway reconstruction, storm sewer improvements and water main replacement on 39th Street from Highland Avenue to Fairview Ave.
Work will also include pedestrian path improvements, driveway apron replacement and parkway sod installation.
LATEST UPDATE
May 29, 2026
- The contractor is expected to mobilize for traffic control starting the week of June 1st. Tree fence installation and preliminary survey may begin as well.
- Initial construction activities to expect include posting traffic control signs/barricades to implement 1-way westbound traffic from Fairview to Washington on 39th Street to prepare for water main installation.
PAST UPDATES
May 22, 2026
The contractor is tentatively planning to start setting up traffic control and mobilizing equipment and materials to the site the first week of June.
April 10, 2026
- Bids were received on April 8. The contract is to be brought before Council for approval on May 5.
- Construction is tentatively expected to begin in late May or early June.
Resources
Project #: ST-058
Start: May 2026
End: November 2026