null
Water

75th St Water Main Improvements

Project Summary

The project will consist of water main replacement on 75th Street from Fairview Avenue to Knottingham Lane. Work will also include patching of the existing roadway where the new water main will be installed, curb removal in select locations, and restoration.

LATEST UPDATE

August 1, 2025

The contractor plans to begin traffic control installation the week of 8/4, as well as erosion control installation and any necessary tree protection fencing.

PAST UPDATES

July 11, 2025

A preconstruction meeting is scheduled for 7/22, at which time the contractor will provide an estimation of schedule/timing for the work.



June 27, 2025

Bids were opened on 6/25/25. The project is expected to go before the Village Council on 7/8/25 & 7/15/25, and construction is expected to begin in early to mid August.



June 20, 2025

The project was advertised on 6/11 with the bid opening scheduled on 6/25. Construction is expected to begin in August.

Resources

Project #: WA-028B

Start: September 2025

End: November 2025

Docs/Links


Project Manager

Brian Gilmore

Staff Engineer

630.434.2453