Sidewalks
Right-of-Way Improvements
Project Summary
This multi-year project consists of replacing existing sidewalk, curb and gutter at various intersections throughout the Village to gain compliance with the Americans with Disabilities Act (ADA).
LATEST UPDATE
September 5, 2025
Sod will be placed on Thursday (9/4) at the intersections of Prairie/Douglas, Prairie/Highland, and Rogers and Highland. Tentative construction dates for the remaining sites are the last two weeks of September
PAST UPDATES
August 29, 2025
Sod will be placed next week at the intersections of Prairie/Douglas, Prairie/Highland, and Rogers/Highland. Tentative construction dates for the remaining sites are the last two weeks of September.
August 22, 2025
Work has been completed at the Prairie/Douglas, Prairie/Highland, and Rogers/Highland intersections. Sod will be placed at these locations later in September after Davis Concrete completes work on the 5 remaining sites.
August 15, 2025
Work has begun at the intersections of Prairie/Douglas, Prairie/Highland, and Highland/Rogers. Contractor plans to work on Saturday 8/16.
August 8, 2025
Removal work will start on 8/8 and replacement work will begin 8/12.
August 1, 2025
Sawcutting will begin August1st or 4th beginning at Douglas/Prairie intersection
July 11, 2025
Project was awarded 7/8.
June 27, 2025
Bids were received 6/25 and are under review.
June 20, 2025
Project is out to bid. Bids due 6/25.
Resources
Project #: S-008
Start: August 2025
End: October 2025