null
Sidewalks

Right-of-Way Improvements

Project Summary

This multi-year project consists of replacing existing sidewalk, curb and gutter at various intersections throughout the Village to gain compliance with the Americans with Disabilities Act (ADA).

LATEST UPDATE

September 5, 2025

Sod will be placed on Thursday (9/4) at the intersections of Prairie/Douglas, Prairie/Highland, and Rogers and Highland. Tentative construction dates for the remaining sites are the last two weeks of September

PAST UPDATES

August 29, 2025

Sod will be placed next week at the intersections of Prairie/Douglas, Prairie/Highland, and Rogers/Highland. Tentative construction dates for the remaining sites are the last two weeks of September.



August 22, 2025

Work has been completed at the Prairie/Douglas, Prairie/Highland, and Rogers/Highland intersections. Sod will be placed at these locations later in September after Davis Concrete completes work on the 5 remaining sites.



August 15, 2025

Work has begun at the intersections of Prairie/Douglas, Prairie/Highland, and Highland/Rogers. Contractor plans to work on Saturday 8/16.



August 8, 2025

Removal work will start on 8/8 and replacement work will begin 8/12.



August 1, 2025

Sawcutting will begin August1st or 4th beginning at Douglas/Prairie intersection



July 11, 2025

Project was awarded 7/8.



June 27, 2025

Bids were received 6/25 and are under review.



June 20, 2025

Project is out to bid. Bids due 6/25.


Resources

Project #: S-008

Start: August 2025

End: October 2025

Docs/Links


Project Manager

Matthew Stern

Staff Engineer

630.434.5463