Sidewalks

Sidewalk Repair & Replacement

Project Summary

This annual project provides for the rehabilitation of sections of sidewalk that have become vertically separated, by saw cutting the lifted edge to provide a smooth walking surface. Sidewalk sections not suitable for rehabilitation are removed and replaced.

LATEST UPDATE

May 8, 2026

  1. Removal and replacement operations are nearly complete. Asphalt and turf restoration operations are ongoing at various locations.
  2. Tuesday, May 12th, the contractor will begin removal and replacement operations in the downtown business district. One of these locations spans the alleyway East of the library.
  3. Signage about alternate traffic patterns during the work will be posted and businesses have been notified. Alternate traffic pattern to last approximately five days while the new concrete cures.

PAST UPDATES

May 1, 2026

Removal and replacement operations are ongoing. Contractor expects to continue pouring concrete into next week, weather pending.



April 24, 2026

Removal and replacement operations are ongoing. Contractor expects to continue pouring concrete into next week, weather pending.



April 17, 2026

Removal operations are ongoing throughout the Village. Contractor expects to begin pouring concrete Friday, 4/17 and into next week, weather pending.



April 10, 2026

Contractor expects to begin work next week, weather pending, beginning with saw cutting.

Resources

Project #: S-006

Start: March 2026

End: April 2026

Docs/Links


Project Manager

Matthew Stern

Staff Engineer

630.434.5463