Drainage and Stormwater
Downtown Stormwater Improvements
Project Summary
St Joseph Creek is conveyed through downtown Downers Grove in a large diameter concrete pipe nearly a mile long. The storm sewer was installed in the 1960's. Maintenance is required to ensure the pipe will continue to convey the creek flow and stormwater runoff safely. In this multi-year project we will clean, repair, and line the pipe.
LATEST UPDATE
August 29, 2025
Cleaning of the pipe is ongoing. Crews will begin grouting to stabilize soils above the pipe.
PAST UPDATES
August 15, 2025
Contractor will be cleaning and televising the 11' pipe. Expect little to no impact to traffic along Curtiss. Driveways are expected to remain accessible.
August 1, 2025
Contractor will be setting up equipment the week of 8/4.
July 25, 2025
Cleaning and inspections for the 11' pipe have been tentatively scheduled for the end of next week. Repairs and lining will follow once the cleaning is complete.
July 11, 2025
Cleaning and inspection for the 11' pipe is tentatively scheduled for the week of 7/14. Repairs and lining under Curtiss between Mackie Pl and Belden Ave is tentatively scheduled for the week of 7/21. Driveways are expected to be open.
June 13, 2025
Ground Penetrating Radar (GPR) will be condeucted above the 11' pipe for repairs. GPR will be conducted on the last week of June. Property owners that may be impacted will recieve a letter.
March 4, 2025
Project information will be shared as the project begins and progresses.
Resources
Project #: SW-90
Start: Spring 2025
End: Fall 2027