St. Joseph creek in Downers Grove
St. Joseph Creek
Drainage and Stormwater

Downtown Stormwater Improvements

Project Summary

St Joseph Creek is conveyed through downtown Downers Grove in a large diameter concrete pipe nearly a mile long. The storm sewer was installed in the 1960's. Maintenance is required to ensure the pipe will continue to convey the creek flow and stormwater runoff safely. In this multi-year project we will clean, repair, and line the pipe.

LATEST UPDATE

August 29, 2025

Cleaning of the pipe is ongoing. Crews will begin grouting to stabilize soils above the pipe.

PAST UPDATES

August 15, 2025

Contractor will be cleaning and televising the 11' pipe. Expect little to no impact to traffic along Curtiss. Driveways are expected to remain accessible.



August 1, 2025

Contractor will be setting up equipment the week of 8/4.



July 25, 2025

Cleaning and inspections for the 11' pipe have been tentatively scheduled for the end of next week. Repairs and lining will follow once the cleaning is complete.



July 11, 2025

Cleaning and inspection for the 11' pipe is tentatively scheduled for the week of 7/14. Repairs and lining under Curtiss between Mackie Pl and Belden Ave is tentatively scheduled for the week of 7/21. Driveways are expected to be open.



June 13, 2025

Ground Penetrating Radar (GPR) will be condeucted above the 11' pipe for repairs. GPR will be conducted on the last week of June. Property owners that may be impacted will recieve a letter.



March 4, 2025

Project information will be shared as the project begins and progresses.

Resources

Project #: SW-90

Start: Spring 2025

End: Fall 2027

Docs/Links


Project Manager

Jildardo Luna

Staff Engineer

630.434.5564