Drainage and Stormwater

Stormwater Quality Improvements

Project Summary

This project provides stormwater infrastructure to remove pollutants from stormwater runoff before it reaches Saint Joseph Creek. A storm structure on Burlington and Mochel will be retro-fitted with a device to improve pollutant removal. A new water quality structure will be installed along Warren Ave between Highland Ave and Washington Ave.

LATEST UPDATE

July 11, 2025

Water quality structure is installed. Lot C and Warren Ave are open to traffic.


PAST UPDATES

July 4, 2025

Lot C along Warren Ave near Main Street station will have reduced parking during construction next week.



June 27, 2025

The water quality structure on Warren Ave will begin construction the week of July 7th.



May 30, 2025

The water quality structure is expected to be installed in July.



May 16, 2025

  1. A new water quality structure will be delivered to Public Works. This structure will be installed along Warren Ave between Highland Ave and Washington Ave.
  2. Expect parking along the track at Lot C to be affected during construction.



Resources

Project #: SW-073

Start: March 2025

End: June 2025

Docs/Links


Project Manager

Jildardo Luna

Staff Engineer

630.434.5564