Sidewalks
Right-of-Way Improvements
Project Summary
This multi-year project consists of replacing existing sidewalk and curb and gutter at various intersections throughout the Village, to gain compliance with the Americans with Disabilities Act (ADA).
LATEST UPDATE
November 22, 2024
This project is complete.
PAST UPDATES
July 12, 2024
Project is substantially complete. Sod restoration is expected to be completed when temperatures allow.
June 28, 2024
- Concrete sidewalk work is nearly complete at all locations. The remaining corners at the intersection of Maple and Cumnor are expected to be completed by the end of next week, weather pending.
- Asphalt and turf restoration are expected to continue into next week, weather pending.
June 21, 2024
- Removals are nearly complete at all locations. Concrete curb and sidewalk work is complete at all locations on Chicago Ave and Venard Rd and 35th St.
- Concrete curb work is complete at 35th and Pomeroy and all Venard locations.
- Concrete work expected to continue into next week, weather pending. Patching work is expected to continue into next week, weather pending.
June 14, 2024
- Removals are nearly complete at all locations. Concrete curb and sidewalk work is complete at all locations on Chicago Ave. Concrete curb work is complete at 35th and Pomeroy and all Venard locations.
- Concrete work expected to continue into next week, weather pending.
May 31, 2024
Saw cutting as preparation for removal has begun. Sidewalk and curb removal should begin next week, weather pending.
May 24, 2024
Rain has impacted the contractors schedule. Project is now expected to begin next week, weather pending.
May 17, 2024
Project expected to begin next week, weather pending.
March 15, 2024
Information and updates will be posted as the project gets underway.
RECENT PROJECT UPDATES
Project #: S-008
Start: April 2024
End: July 2024