photo of a random sidewalk
Sidewalks

Sidewalk Repair and Replacement

Project Summary

This annual project provides for the repair and/or replacement of sections of sidewalk due to hazardous conditions.

LATEST UPDATE

July 7, 2023

Project is substantially complete. Punch list will be issued to the contractor next week.

PAST UPDATES

June 30, 2023

Concrete work is complete at all locations. Restoration work is expected to continue into next week, weather pending.


June 23, 2023

Contractor has begun removal and replacement of locations throughout the Village. Removal, framing, pouring and restoration work is expected to continue into next week, weather pending.


June 16, 2023

Contractor has begun removal and replacement of locations throughout the Village. Removal, framing, and pouring work is expected to continue into next week, weather pending.


June 9, 2023

Contractor has begun removal and replacement of locations throughout the Village. Removal, framing, and pouring work is expected to continue into next week, weather pending.


June 2, 2023

Sidewalk replacement work in the Downtown Business District is complete. Work throughout the rest of town is expected to begin next week, weather pending.


May 26, 2023

Replacement work in the Downtown Business District is scheduled to begin the week of 5/29, weather pending.


May 19, 2023

Contractor will continue saw cutting into next week, weather pending.


May 12, 2023

Saw cutting continues.


April 28, 2023

Contractor will continue saw cutting into next week, weather permitting.


April 7, 2023

Contractor will continue saw cutting into next week, weather permitting.


March 31, 2023

Saw cutting continues into next week, weather permitting.


March 17, 2023

Contractor is scheduled to begin work on Monday, weather pending.


RESOURCES

Project #: S-006

Start: March 2023

End: June 2023

Docs/Links

MAP

Project Manager

Matthew Stern

Staff Engineer

630.434.5463