Drainage and Stormwater

Storm Sewer Replacement

Project Summary

This project addresses the rehabilitation of storm culverts under Saratoga Ave south of 35th St, maintenance of the box culvert and St Joseph's Creek at Curtiss St, and the replacement of storm discharges into Prentiss Creek by Prentiss Dr and Bolson Dr.

LATEST UPDATE

September 22, 2023

All punch list items have been addressed. Project is complete.

PAST UPDATES

July 28, 2023

The Pipe Liner on Saratoga Ave was completed 7/27. Tree fence will be removed the week of 7/31. Contractor will begin punchlist work in the coming weeks.


July 14, 2023

Installation of the Pipe Liner on Saratoga Ave is scheduled for the middle of the week of 7/24, weather pending.


June 30, 2023

The installation of the pipe lining at Saratoga Ave is scheduled for the week of 7/17, weather pending.


June 16, 2023

The Prentiss Dr and Bolson Dr locations are substantially completed. The pipe lining at Saratoga Ave will be occurring in July.


June 9, 2023

Work at the Prentiss Dr and Bolson Dr locations started this week. Work at these locations should be substantially complete the week of 6/12, weather pending.


May 19, 2023

Contractor is scheduled to commence work the Week of June 5. The pipe lining at Saratoga Ave will occur late June/early July.


April 14, 2023

Contract was awarded at the April 11, 2023, Village Council meeting.


RESOURCES

Project #: SW-070

Start: May 2023

End: July 2023

Docs/Links

MAP

Contact

Phil Hyma

Staff Engineer

630.434.5488