Drainage and Stormwater

Curtiss & Glenview Improvements

Project Summary

This project includes design and installation of a pump station and drainage storage to help reduce the frequency of roadway flooding at the intersection of Curtiss Street and Glenview Avenue.

LATEST UPDATE

August 11, 2023

Plan design is continuing, but construction could be delayed due to supply issues for the pumps.

PAST UPDATE


RESOURCES

Project #: SW-098

Start: September 2023

End: November 2023