Watermain Replacements (Contract C)

 

Table #: Project completion and contact information.
Project InformationData
Project # WA-028
Category Water
Start Date June, 2018
End Date September, 2018
Project Status

               Green
(Project is on schedule.)         

Village Contact

Scott Vasko, Staff Engineer (630) 434-6804

Project Summary

The project will consist of the water main replacement on Hill Street from Grand Avenue to Fairview Avenue, Curtiss Street from Washington Street to Mackie Place, and Belden Avenue from Curtiss Street to Maple Avenue. Work will also include patching of the existing roadway where the new water main will be installed, sidewalk improvements at the intersections and street resurfacing.

The work will be completed in phases:

  1. Pavement removal and excavation
  2. Installation of main line water main
  3. Testing and chlorination of main line water main
  4. Connection of existing water service lines to new main line water main
  5. Pavement, concrete and turf restoration

Project Alerts

 

Recent Progress

10/26/2018

Project is substantially complete. A punchlist will be generated and sent to the contractor.

10/19/2018

The contractor is finishing restoration on Curtiss and Belden.

10/12/2018

This week

Contractor worked on restoration on Curtiss and will continue restoration next week.

Next week

The Village will perform a final walk through and generate a punchlist.

10/5/2018

This week

The contractor completed all the paving on Curtiss, Mackie, and Belden this week. The contractor completed parkway restoration on Hill. The contractor started parkway restoration on Belden, Curtiss, and Mackie this week.

Next week

Next week the contractor is scheduled to complete restoration on Curtiss, Mackie, and Belden.

9/28/2018

This week

The contractor completed the first layer of asphalt on Belden, Curtiss, and Mackie this week.

Next week

The contractor is scheduled to install the final layer of asphalt next week on Belden, Curtiss, and Mackie next week. The contractor is scheduled to start on parkway restoration next week.

 

9/21/2018

This week

The contractor completed grinding on Mackie, Belden, and Curtiss this week. The contractor also patched the water main trench on Curtiss. The contractor started concrete work on Curtiss, Belden, and Mackie this week and is scheduled to complete all concrete work next week.

Next week

The contractor is scheduled to complete the first layer of asphalt on Mackie, Belden, and Curtiss next week.

9/14/2018

This week

The contractor completed all water main installation on Curtiss and Belden this week.

Next week

Next week the contractor is scheduled to start concrete work on Belden, Curtiss and Mackie. The contractor is scheduled to start sod installation on Belden, Curtiss and Mackie next week. The contractor is also scheduled to start sod installation on Hill.

9/7/2018

This week

Contractor chlorinating and testing water main on Belden and Curtiss.

Next week

The contractor is scheduled to start water services on Belden and Curtiss next week after water main passes testing.

8/31/2018

This week

Contractor completed all mainline water main on Belden and Curtiss this week.

Next week

Next week contractor will be chlorinating and testing water main on Curtiss and Belden.

8/24/2018

This week

Contractor continued water main installation on Curtiss and Belden this week.

Next week

Contractor is scheduled to have all mainline water main installed on Curtiss and Belden next week and will start testing. Contractor is completing parkway restoration on Hill this week and next week.

8/17/2018

This week: Contractor completed all paving on Hill. Contractor began water main installation on Belden and Curtiss.
Next week: The contractor is scheduled to continue water main installation on Belden and Curtiss.

8/10/2018

This week: Contractor completed all water main work on Hill this week. Contractor will also complete all concrete work on Hill this week.
Next week: Next week the contractor will be grinding, patching and installing the first layer of asphalt on Hill. The contractor will be starting water main installation on Belden at Maple next week. The contractor will also be starting the water main installation on Curtiss at Washington at the end of next week.

8/3/2018

Contractor finishing services at another location and is scheduled to be in the end of next week to install water services on Hill. Contractor also scheduled to make connection at Hill and Fairview and abandon existing main on Hill. Contractor completed sawcutting pavement on Curtiss and Belden. Work scheduled to start on Belden and Curtiss the week of the 13th.

7/27/2018

This week

The contractor is doing testing on the new main this week.

Next week

Next week the contractor is scheduled to receive test results on new main and possibly start water service installations.

7/20/2018

This week

All water main on Hill has been installed.

Next week

The contractor is scheduled to be testing and chlorinating the new water main.

7/13/2018

This week

Water main installation has started on Hill between Fairview and Grand.

Next week

The contactor is scheduled to complete all mainline water main on Hill and start testing.

7/6/2018

Water main installation is scheduled to begin on Hill Street between Grand and Fairview next week.

6/29/2018

Water main installation will begin on Hill Street between Grand and Fairview the week of July 9.

6/15/2018

Project was awarded this week and is scheduled to begin in July. 

5/25/2018

The project is scheduled to be awarded on June 12.