Watermain Replacements (Contract B)

 

Project InformationData
Project #  IEPA19B
Category Water
Start Date June/July 2019
End Date October 2019
Project Status

               Green
(Project is on schedule.)

Village Contact

Scott Vasko, Staff Engineer (630) 434-6804


Project Summary

The project will consist of the water main replacement on Jefferson Avenue from Dunham Road to Brookbank Road, Almond Court from Downers Drive to cul-de-sac, and Pomeroy Road from 35th Street to cul-de-sac. Work will also include patching of the existing roadway where the new water main will be installed, sidewalk improvements at the intersections, and street resurfacing.

 

The work will be completed in phases:

  1. Pavement removal and excavation
  2. Installation of main line water main
  3. Testing and chlorination of main line water main
  4. Connection of existing water service lines to new main line water main
  5. Pavement, concrete and turf restoration

Project Alerts

 

Recent Progress

10/18/19

Contractor completed first layer of asphalt on Almond, Jefferson, and Pomeroy this week. Next week, contractor is scheduled to do manhole adjustments on Jefferson and Almond.

10/11/19

Contractor completed patching on Jefferson and Almond this week, and all water main work on Pomeroy.

Next week contractor is scheduled to grind Almond and Jefferson, and possibly put down first layer of asphalt on both.

10/04/19

Contractor completed all concrete work on Almond and Jefferson this week.

Contractor is scheduled to install water services on Pomeroy next week. Contractor is scheduled to patch Almond and Jefferson next week and possibly grind the remainder of Almond and Jefferson.

9/27/19

Contractor completed mainline water main work on Pomeroy and will be testing new water main next week on Pomeroy. Contractor is scheduled to be in next week for concrete work on Almond and Jefferson.

9/20/19

All water main work on Almond was completed this week. Contractor started water main installation on Pomeroy this week. Next week contractor is scheduled to start concrete work on Almond and Jefferson and continue water main on Pomeroy.

9/13/19

All water main work on Jefferson was completed this week.

Contractor is scheduled to complete water services and all water main work on Almond Ct next week. Contractor will begin to mobolize to Pomeroy to start work there next week.

9/6/19

Water main installation completed on Almond this week, and water main testing has started. Water service installations have begun on Jefferson this week. Next week contractor is scheduled to finish water services on Jefferson and possibly start water services on Almond.

8/30/19

Water main installation completed on Jefferson this week, and water main testing has started. Water main installation on Almond Court began this week. Next week contractor is scheduled to finish water main installation on Almond and begin testing on Almond. Contractor is also scheduled to start water service installations on Jefferson.

8/16/19

Water main installation started on Jefferson at Dunham this week. Contractor is scheduled to continue water main installation on Jefferson next week.

8/9/19

Contractor installed tree protection and delivered materials on Jefferson. Water main installation will begin on Jefferson next week at Dunham and progress to the west.

6/28/19

The preconstruction meeting was held last week, and the contractor is scheduled to start work on Jefferson in late July or early August. Notices will be mailed to residents closer to the start of work.

6/14/19

The contract was approved on the June 11, 2019 Council Agenda. A pre-construction meeting will be scheduled the week of June 17, 2019.

4/24/19

The project is out for bid. Bids will be opened May 3, 2019. Construction is expected to begin in late June/early July.