Skip to main content

Watermain Replacements (Contract B)

 

Project InformationData
Project #  IEPA19B
Category Water
Start Date June/July 2019
End Date October 2019
Project Status

               Green
(Project is on schedule.)

Village Contact

Scott Vasko, Staff Engineer (630) 434-6804


Project Summary

The project will consist of the water main replacement on Jefferson Avenue from Dunham Road to Brookbank Road, Almond Court from Downers Drive to cul-de-sac, and Pomeroy Road from 35th Street to cul-de-sac. Work will also include patching of the existing roadway where the new water main will be installed, sidewalk improvements at the intersections, and street resurfacing.

 

The work will be completed in phases:

  1. Pavement removal and excavation
  2. Installation of main line water main
  3. Testing and chlorination of main line water main
  4. Connection of existing water service lines to new main line water main
  5. Pavement, concrete and turf restoration

Project Alerts

 

Recent Progress

8/16/19

Water main installation started on Jefferson at Dunham this week. Contractor is scheduled to continue water main installation on Jefferson next week.

8/9/19

Contractor installed tree protection and delivered materials on Jefferson. Water main installation will begin on Jefferson next week at Dunham and progress to the west.

6/28/19

The preconstruction meeting was held last week, and the contractor is scheduled to start work on Jefferson in late July or early August. Notices will be mailed to residents closer to the start of work.

6/14/19

The contract was approved on the June 11, 2019 Council Agenda. A pre-construction meeting will be scheduled the week of June 17, 2019.

4/24/19

The project is out for bid. Bids will be opened May 3, 2019. Construction is expected to begin in late June/early July.