Skip to main content

Watermain Replacements (Contract A)

 

 

 

Project InformationData
Project #  IEPA18A, WA-028A
Category Water
Start Date June, 2018
End Date September, 2018
Project Status

               Green
(Project is on schedule.)

Village Contact

Scott Vasko, Staff Engineer (630) 434-6804

 

Project Summary

 

The project will consist of the water main replacement on Fairmount Avenue from 55th Street to 59th Street, Washington Street from Summit Street to 55th Street, and Williams Street from 39th Street to 41st Street. Work will also include patching of the existing roadway where the new water main will be installed, sidewalk improvements at the intersections and street resurfacing.

The work will be completed in phases:

  1. Pavement removal and excavation
  2. Installation of main line water main
  3. Testing and chlorination of main line water main
  4. Connection of existing water service lines to new main line water main
  5. Pavement, concrete and turf restoration

Project Alerts

 

Recent Progress

10/26/2018

Project is substantially complete. A punchlist will be generated and sent to the contractor.

10/19/2018

The contractor is working on parkway restoration on Williams and Washington.

10/12/2018

The contractor is scheduled to complete parkway restoration on Williams next week.

10/5/2018

This week

The contractor completed all paving on Williams and Washington this week. The contractor completed parkway restoration on Fairmount this week.

Next week

The contractor started parkway restoration on Washington this week. The contractor is scheduled to continue parkway restoration on Washington and Williams next week.

9/28/2018

This week

The contractor completed the first layer of asphalt on Williams and Washington this week.

Next week

The contractor is scheduled to install the final layer of asphalt next week on Washington and Williams next week. The contractor is scheduled to start on parkway restoration next week.

9/21/2018

This week

The contractor completed grinding both Williams and Washington this week. The contractor also patched the water main trenches on Williams and Washington.

Next week

Next week the contractor is scheduled to complete the first layer of asphalt on both Williams and Washington. The contractor will also be scheduled to start parkway restoration on streets.

9/14/2018

This week

Contractor completed all concrete work on Washington and Williams this week.

Next week

Next week the contractor is scheduled to grind both Washington and Williams. The contractor will also start patching and paving Williams and Washington next week. The contractor is also scheduled to start sod installation on Fairmount.

9/7/2018

This week

Contractor completed water services on Williams this week. Contractor was delayed starting concrete work on Washington because of weather.

Next week

Next week contractor is scheduled to start concrete work on both Washington and Williams.

8/31/2018

This week

Contractor completed all water main work on Washington this week. Contractor began water service installations on Williams this week.

Next week

Next week contractor is scheduled to continue water service installations on Williams. Contractor is scheduled to remove and replace curb and sidewalks on Washington next week.

8/24/2018

Contractor is testing and chlorinating water main on Williams this week and next week. The contractor is installing water services on Washington this week and should have them completed early next week. The contractor is scheduled to have all water main work on Washington completed next week. Contractor is also working on parkway and driveway apron restoration on Fairmount this week and next week.

 

8/17/2018

This week

Contractor completed all paving on Fairmount this week. The contractor continued water main installation on Williams this week.

Next week

The contractor is scheduled to complete all mainline water main installation on Williams and begin chlorinating and testing the new main. The contractor is scheduled to start water service installations on Washington next week. 

8/10/2018

This week
Contractor completed all water main work on Fairmount this week. The contractor also completed all concrete work on Fairmount this week.The first layer of asphalt is expected to be paved throughout the project on Monday, August 13th. In-pavement structures and traffic signal detector loops are expected to be adjusted and installed on Tuesday, August 14th. Surface asphalt will tentatively be placed on Wednesday and Thursday, August 15th and 16th. Throughout this work, the landscaper may be onsite preparing restoration areas, filling in areas behind curb and sidewalk, and spreading topsoil. Due to hot temperatures, IDOT specifications state that sod cannot be placed in the month of August. The landscaper will be onsite in September when temperatures are less than 80 degrees to install the sod. It is the responsibility of the contractor to water the sod and residents will not be asked or expected to water or mow during its establishment period.

Next week
The contractor will continue installing water main on Williams next week. The contractor is also scheduled to complete pavement patching and the installation of the first layer of asphalt on Fairmount next week.

8/3/2018

This week

Contractor completed water main installation on Washington between 55th and Summit. Contractor started water main installation on Williams at 39th Street. Contractor continued water service installations on Fairmount at the south end.

Next week

Contractor is scheduled to complete water services and final connections on Fairmount. Contractor is scheduled to continue water main installation on Williams. Contractor also scheduled to start concrete work on Fairmount. New main on Washington will be tested and chlorinated.

7/27/2018

This week

Contractor started water main installation on Washington this week north of 55th.

Next week

The contractor is scheduled to complete the main line water main installation on Washington and possibly start the water main installation on Williams between 41st and 39th. The contractor is also scheduled to resume water service installations on Fairmount.

7/20/2018

This week

Contractor installing water services on the north half of Fairmount.

Next week

The contractor is scheduled to continue water service installations on Fairmount and start water main installation on Washington.

7/13/2018

This week

All mainline water main has been installed on Fairmount from 55th to 59th. 

Next week

The contractor is scheduled to start installing water services at the north end of Fairmount. Notices have been delivered to residents on Washington about work starting the week of July 23. 

7/6/2018

This week

All water main north of the creek on Fairmount has been installed. The new main was connected at 55th.

Next week

The contractor is scheduled to continue installation of the water main on Fairmount south of the creek.

6/29/2018

This week

The contractor continued water main installation on Fairmount south of the creek. The contractor installed the water main under the creek on Fairmount.

Next week

The contractor will continue the water main installation south of the creek. The contractor is scheduled to connect the new water main at 55th and Fairmount.

6/22/2018

This week

The water main installation continued on Fairmount between 55th St and the creek. The contractor dug the auger pit for the water main installation under the creek.

Next week

The contractor is scheduled to install the water main under the creek and continue water main installation on Fairmount south of the creek.

6/15/2018

This week

Water main installation began on Fairmount.

Next week

Water main installation will continue on Fairmount. 

6/8/2018

This week

Tree protection is currently being installed on Fairmount between 55th and 59th street. 

Next Week

Materials are scheduled to be delivered to Fairmount. Water main installation is scheduled to start on Fairmount at 55th Street. 

5/25/2018

The project was awarded on May 8, 2018. Work is scheduled to begin on Fairmount between 55th and 59th Street the week of June 4. 

5/4/2018

The project is scheduled to be awarded on 5/8/2018.