Skip to main content

Watermain Replacements (Contract A)

 

 

 

Project InformationData
Project #  IEPA19A
Category Water
Start Date June/July 2019
End Date October 2019
Project Status

               Green
(Project is on schedule.)

Village Contact

Scott Vasko, Staff Engineer (630) 434-6804

 

Project Summary

 

The project will consist of the water main replacement on Wisconsin Avenue from Walnut Avenue to Belmont Road, and Northcott Avenue from Prairie Avenue to Warren Avenue. Work will also include patching of the existing roadway where the new water main will be installed, sidewalk improvements at the intersections, and street resurfacing.

The work will be completed in phases:

  1. Pavement removal and excavation
  2. Installation of main line water main
  3. Testing and chlorination of main line water main
  4. Connection of existing water service lines to new main line water main
  5. Pavement, concrete and turf restoration

Project Alerts

 

Recent Progress

10/18/19

Contractor completed storm sewer installation on Northcott this week and will start water service installations next week. Contractor completed the first lift of asphalt on Wisconsin this week and is scheduled to do manhole adjustments next week.

10/11/19

Contractor completed main line water main work on Northcott and started storm sewer installation on Northcott. Contractor completed patching on Wisconsin and started grinding.

Next wek contractor is scheduled to continue on storm sewer installation on Northcott and possibly put down first layer of asphalt on Wisconsin.

10/04/19

Contractor completed all concrete work on Wisconsin this week and continued water main installation on Northcott. Contractor also completed pavement patching on Wisconsin this week.

Contractor is scheduled to continue water main installation and start sewer installation on Northcott next week. Contractor is scheduled to grind Wisconsin next week.

9/27/19

Contractor completed all water main work on Wisconsin and started concrete work on Wisconsin. Contractor started water main work on Northcott starting at Warren.

Next week, contractor will continue water main installation on Northcott. Contractor is scheduled to complete concrete work on Wisconsin, and possibly start patching water main trench on Wisconsin.

9/20/19

Contractor working on connections on Wisconsin between Katrine and Walnut. Contractor completed construction layout and started tree protection installation on Northcott. Next week contractor is scheduled to complete all water main work on Wisconsin. Next week contractor is scheduled to start water main installtion on Northcott.

9/13/19

Contractor testing new water main on Wisconsin between Katrine and Walnut this week, and is working on connections on Wisconsin between Janes and Katrine.

Next week contractor is scheduled to continue work on connections on Wisconsin between Katrine and Walnut.

9/6/19

Contractor testing new water main on Wisconsin between Janes and Katrine this week, and completed all connections on Wisconsin between Janes and Belmont. Next week contractor is scheduled to continue work on connections on Wisconsin between Janes and Katrine.

8/30/19

Contractor testing new water main on Wisconsin between Janes and Katrine this week, and making connections on Wisconsin between Janes and Belmont. Next week contractor is scheduled to complete all connections on Wisconsin between Janes and Belmont.

8/23/19

Contractor completing valves and fire hydrant installations this week on Wisconsin. Contractor will be testing new water main on Wisconsin between Janes and Katrine next week. Contractor will start making connections to the new water main next week between Belmont and Janes.

8/16/19

Contractor completed water main installation across Walnut this week. Contractor is installing valves and fire hydranrts this week. Contractor is scheduled to install valves and fire hydrants next week on Wisconsin.

8/9/19

Water main installation on Wisconsin has been installed to Walnut Ave. Contractor will be installing fire hydrants and valves next week.

7/26/19

Water main installation on Wisconsin continues between Janes and Katrine. Contractor will be installing water main and fire hydrants next week.

7/19/19

Water main installation on Wisconsin continues between Belmont and Janes. Contractor will be installing water main and start fire hydrant installations next week.

7/5/19

Utility location was completed this week. Contractor wil begin installing tree protection and delivering materials on Wisconsin next week. Water main installation will begin on Wisconsin next week at Belmont and progress to the west.

6/28/19

The preconstruction meeting was held last week, and the contractor is scheduled to start work on Wisconsin the week of July 8th. Notices were mailed this week to the businesses on Wisconsin.

6/14/19

The contract was approved on the June 11, 2019 Council Agenda. A pre-construction meeting will be scheduled the week of June 17, 2019.

4/24/19

The project is out for bid. Bids will be opened May 3, 2019. Construction is expected to begin in late June/early July.