Table #: Project completion and contact information.
Project InformationData
Project # SW-070
Category Drainage
Start Date April 2021
End Date June 2021
Project Status

               Green
          On Schedule                        

Village Contact

Katherine Zirbel, Staff Engineer (630) 434-5488

Project Summary

This project includes culvert pipe and headwall replacement where Prentiss Creek crosses Springside Ave (just north of Bolson Dr), storm sewer replacement, roadway and sidewalk replacement, installation of a ornamental fence adjacent to the sidewalk, and streambank stabilization. The work will require closure of Springside Ave. A detour route will be posted.

 

Project Alerts

 

Recent Progress

10/23/20

Due to the lead time on material required to complete the project, the project is now expected to begin in Spring 2021.

9/4/20

The construction contract was approved at the September 8th Council Meeting. A preconstruction meeting is planned for the week of September 14th. Construction notices will be sent out to those impacted by the project when a construction schedule is established.

8/28/20

Bids have been received. The construction contract is scheduled for Council approval in September.

8/14/20

The project is currently out to bid, with bids due 8/21/20.