Sidewalk Repair/Replacement

 

Project InformationData
Project # S-006
Category Sidewalks
Start Date Week of July 16, 2018
End Date

August, 2018

Percent Complete
Village Contact Matthew Stern, Staff Engineer (630) 434-5463

Project Summary

This project provides for the replacement or rehabilitation of sidewalk tripping hazards or sidewalk sections deteriorated beyond its useful life. Work for this project will occur at multiple locations around the Village including work within the Downtown Business District (DBD). 

Project Alerts

Residents/business owners aware of sections of sidewalk in need of repair should contact the Public Works Department at 630-434-5460

Recent Progress

10/12/2018

Project is substantially complete. A "Punch List" of cleanup items has been generated and sent to the contractor.

8/10/2018

Majority of the sidewalk locations throughout the Village have been replaced. The Contractor is expected to begin repairing driveway and parkway impacts within the next couple weeks.

8/3/2018

Majority of the sidewalk locations throughout the Village have been replaced. The Contractor is expected to begin repairing driveway and parkway impacts within the next couple weeks.

7/27/2018

Majority of the sidewalk locations throughout the Village have been replaced. Contractor will be repairing driveway and parkway impacts over the next week.

7/13/2018

Weather pending, the contractor is expected to begin sidewalk removal and replacement within the Downtown Business District (DBD) the week of July 16, 2018. All disturbed sidewalk within the DBD will be either temporarily or permanently restored by Thursday afternoon.

7/6/2018

The contractor is expected to begin sidewalk removal and replacement within the Downtown Business District (DBD) the week of July 16, 2018. All disturbed sidewalk within the DBD will be either temporarily or permanently restored by Thursday afternoon on July 19.