Right-of-Way Accessibility Improvements

Project InformationData
Project #  S-008
Category Sidewalks
Start Date October, 2018
End Date October, 2018
Project Status

 

             Green
(Project is on schedule)


Village Contact

Matthew Stern, Staff Engineer (630) 434-5463

Project Summary

Project consists of improvements to public right of way pedestrian access routes, mainly upgrades to the existing sidewalk ramps. Proposed locations include:

-Coral Berry Ln and Venard Rd

-Warren Ave and Cornell Ave

-Norfolk St and Dunham Rd

-Stanford Ave and Dunham Rd

-Chicago Ave and Forest Ave

 

 

Recent Progress

11/2/2018

Sod restoration is underway. Sod restoration and road patching are expected to be completed next week.

10/19/2018

All concrete sidewalks and curbs have been poured. Contractor will begin asphalt and turf restoration work next week.

10/12/2018

Contractor is scheduled to mobilize to all locations next week to begin sidewalk removal and begin sidewalk replacement.

8/24/2018

Construction contract awarded at August 7, 2018 Council Meeting. Pre-construction work underway.

7/27/2018

Project expected to be awarded in August 2018.

7/13/2018

Bids for this project will be opened on July 19, 2018.