Table 1: Project completion and contact information.
Project InformationData
Project # P-005
Category Parking 
Start Date June 22, 2015 
End Date October 2015
Project Status

             Yellow
(Project is behind schedule.)

Village Contact Jim Tock, Engineering Manager (630) 434-2453  

Project Summary

This project involves the reconstruction of commuter Parking Lot H, which is located at the southwest corner of the Belmont railroad crossing. Work includes full pavement replacement, storm sewer replacement, installation of a new and improved lighting system, and installation of a bio swale median. The new parking lot will also include a wheelchair accessible north-south walkway and a higher capacity bike rack next to the station.  The project will be funded by both the Village of Downers Grove and Metra.

 

Project Milestones Phase 1 Phase 2  Phase 3 
                 (Status: Pending, In-progress, Complete)
Replacement of storm sewer Complete  Complete Complete
Pavement removal and re-grading Complete Complete Complete
Placement of new curb and gutter, sidewalk, and pavement Complete Complete Complete
Installation of lighting system Complete Complete N/A 
Landscaping, including bioswale In-progress In-progress In-progress
Pavement markings and signage Complete Complete N/A

Parking  Impacts

Parking at and in the vicinity of Parking Lot H has returned to pre-construction status.  Daily-fee parking spaces are now available along the south end of Parking Lot H.  Additional Lot H permit parking is no longer available.  The temporary Overlay Parking Lot H lot off Chase Ave is now closed.

Project Alerts

Recent Progress

10/14/2016

The contractor is continuing to work on various punch list items.

9/30/2016

The contractor is continuing to work on various punch list items.

9/2/2016

The contractor is continuing to work on various punch list items.

7/15/2016

The contractor is continuing to work on various punch list items.

7/8/2016

The contractor is continuing to work on various punch list items.

7/1/2016

The contractor is continuing to work on various punch list items.

6/24/2016

The contractor is continuing to work on various punch list items.

6/10/2016

The contractor is continuing to work on various punch list items.

6/3/2016

Last week, the contractor completed installation of the bio-swale soil mix and all plantings. Landscape restoration is complete. The contractor is expected to continue working on various punch list items.

5/27/2016

Last week, the contractor completed placement of mulch and placement of native grasses, bushes, and trees in all areas except the bio-swale. This week, the contractor completed installation of the bio-swale soil mix and all plantings. Landscape restoration is complete. Next week, the contractor is expected to continue working on various punch list items.

5/20/2016

Last week, the contractor placed mulch and began preparing landscape islands for plantings. This week, the contractor completed placement of mulch and placement of native grasses, bushes, and trees in all areas except the bio-swale. Next week, the contractor is expected to continue working on landscape restoration and various punch list items.

5/13/2016

No work took place last week. This week, the contractor continued landscape restoration and various punch list items. Next week, the contractor is expected to continue working on landscape restoration and various punch list items.

5/6/2016

No work took place last week. This week, the contractor continued landscape restoration and various punch list items. Next week, the contractor is expected to continue working on landscape restoration and various punch list items.

4/29/2016

Last week, the contractor continued working on landscape restoration. No work took place this week. Next week, the contractor is expected to continue working on landscape restoration and various punch list items.

4/14/2016

This week, the contractor continued working on landscape restoration and various punch list items. Next week, the contractor is expected to continue working on landscape restoration and various punch list items.

4/8/2016 

Last week, the contractor installed handrails. This week, the contractor began landscape restoration as well as other miscellaneous items. Next week, the contractor is expected to continue landscape restoration and begin working on various punch list items. We do not anticipate any impacts to parking while this work is taking place.

12/17/2015

The contractor has completed pavement striping for Phase 2, installation of daily-fee signs for Phase 2, and installation of the lighting system for Phases 1 and 2. Restoration of disturbed landscape areas will continue throughout the winter as weather permits. Any remaining landscape restoration, including installation of the bio-swale near the center of the site, will be completed in spring 2016.

Please see "Project Alerts" section above for information regarding updates to construction phasing and impacts to both permit and daily-fee parking for Parking Lot H.

12/4/2015 

This week, the contractor completed striping for Phase 2, continued installation of posts and signs for daily-fee spaces, continued installation of lighting system, and began restoration of disturbed landscape areas.

Next week, the contractor is expected to complete installation of the lighting system and continue landscape restoration.

Please see "Project Alerts" section above for information regarding updates to construction phasing and impacts to both permit and daily-fee parking for Parking Lot H.

11/24/2015

This week, the contractor expects to complete striping for Phase 2, installation of lighting system, and installation of posts for daily-fee number signs.

Next week, the contractor is expected to begin restoration of disturbed areas.

Please see "Project Alerts" section above for information regarding updates to construction phasing and impacts to both permit and daily-fee parking for Parking Lot H.

11/20/2015 

 

This week, the contractor completed placement of asphalt for Phases 2 and 3 and completed striping for Phase 2. The contractor also continued installation of light pole foundations and poles.

Next week, the contractor is expected to continue installation of the lighting system, continue restoration of disturbed areas, and begin installation of posts for daily-fee number signs.

Please see "Project Alerts" section above for information regarding updates to construction phasing and impacts to both permit and daily-fee parking for Parking Lot H.

 

11/13/2015  

This week, the contractor completed pavement removal and placement of stone base for Phase 3 and placement of curb and gutter and sidewalk for Phases 1 and 2. Placement of the asphalt for Phases 2 and 3 this week was delayed by weather.

Next week, the contractor is expected to complete placement of the first layer of asphalt for Phases 2 and 3. Please see "Project Alerts" section above for information regarding impacts to traffic due to Phase 3 work. Phase 3 is expected to be open to traffic next week.

11/6/2015 The contractor placed the first layer of asphalt for Phase 2 last week.

This week, the contractor completed storm sewer installation for Phase 2 and began pavement removal and placement of stone base for Phase 3. Next week, the contractor is expected to complete placement of the first layer of asphalt for Phase 2 and begin placement of the first layer of asphalt for Phase 3. Please see "Project Alerts" section above for information regarding impacts to traffic due to Phase 3 work. Phase 3 is expected to be open to traffic next week.

10/30/2015 

This week, the contractor completed placement of stone base for Phase 2. Placement of asphalt has been delayed by weather.

Next week, the contractor is expected to begin placement of the first layer of asphalt for Phase 2. The contractor is expected to transition from Phase 2 to Phase 3 next week. Please visit this webpage for schedule updates and information in regards to impacts to traffic.

10/23/2015 This week, the contractor completed earth excavation and began stone placement for Phase 2. Next week, the contractor is expected to complete placement of the stone base and begin placement of the first layer of asphalt for Phase 2. The contractor is expected to transition from Phase 2 to Phase 3 next week. Please visit this webpage for schedule updates and information in regards to impacts to traffic.

10/16/2015 

This week, the contractor continued earth excavation and began placement of the stone base for Phase 2.

Next week, the contractor is expected to complete placement of the stone base and begin placement of the first layer of asphalt for Phase 2.

10/9/2015 

This week, the contractor continued curb and gutter and sidewalk installation and earth excavation for Phase 2.

Next week, the contractor is expected to continue curb and gutter and sidewalk installation, earth excavation, and placement of stone base for Phase 2

10/2/2015

 This week, the contractor continued storm sewer installation and earth excavation and began installation of curb and gutter and sidewalk for Phase 2.

Next week, the contractor is expected to complete storm sewer installation and continue earth excavation and installation of sidewalk and curb and gutter for Phase 2.

9/18/2015 

This week, the contractor continued pavement removal and began storm sewer installation and earth excavation for Phase 2.

Next week, the contractor is expected to continue earth excavation and complete storm sewer installation for Phase 2.

9/11/2015

 This week, the contractor completed curb and gutter removal and continued pavement removal for Phase 2.

Next week, the contractor is expected to continue pavement removal and begin storm sewer installation for Phase 2.

9/4/2015 

This week, the contractor placed final lift of asphalt and striped Phase 1 of construction. Contractor has begun pavement and curb removal for Phase 2.

Next week, the contractor is expected to continue removal of pavement and curb and begin installation of storm sewer for Phase 2.

8/28/2015 

This week, the contractor completed fine grading of the stone base and placement of the first lift of asphalt for Phase 1. Next week, the contractor is expected to complete asphalt placement, stripe and prepare Phase 1 of construction for commuter traffic. The actual transition date from Phase 1 to Phase 2 will be posted on the website along with detailed information regarding impacts to traffic.


Please be advised construction phasing, temporary off-site parking and planned access into and out of Parking Lot H has changed. Please see the revised Parking Lot H Improvements - Parking Guide During Construction above for more information. Paper copies of the updated parking guide are also available on the Belmont Station platforms.

 

8/21/2015 

This week, the contractor has continued fine grading the stone base for new asphalt.

Next week, the contractor is expected to finish fine grading of the stone base, place asphalt, stripe and prepare Phase 1 of construction for commuter traffic. The actual transition date from Phase 1 to Phase 2 will be posted on the website along with detailed information regarding impacts to traffic.

8/19/2015 Special Update (alert): Temporary daily-fee parking on Haddow Ave west of Belmont Rd will no longer be available beginning Wednesday, August 26th, 2015. This location will return to 4-hour parking from 6am to 6pm on Wednesday, August 26th, 2015.

8/14/2015 Placement of curb and gutter and sidewalk in Phase 1 has been completed. Preparation for the installation of light pole bases is underway.

7/31/2015 Excavation for and preparation of sub-grade for new pavement, curb and gutter, and sidewalk is complete for Phase 1. Placement of stone base, curb and gutter, and sidewalk is underway for phase 1.

7/17/2015 Excavation for and preparation of sub-grade for new pavement, curb and gutter, and sidewalk is still underway for Phase 1.

7/10/2015 The contractor has completed pavement and curb and gutter removal and storm sewer installation for Phase 1. Excavation for and preparation of sub-grade for new pavement, curb and gutter, and sidewalk is underway for Phase 1.

7/3/2015 The contractor is continuing to remove pavement and curb and gutter for Phase 1. Installation of storm sewer has begun.

6/26/2015 The contractor has mobilized and has begun pavement and curb and gutter removal for Phase 1 of construction.

6/12/2015   Contractor is scheduled to mobilize to site on 6/22/15.  "The Parking Lot H Improvements - Parking Guide During Construction" will be in effect starting the morning of 6/22/15.  

5/29/2015  Construction contract has been awarded and project scheduling is underway. 

April 2015 Bids have been opened; Contract currently under review.