Project InformationData
Project # SW-096
Category Drainage
Start Date August 2022
End Date October 2022
Project Status

Complete

Village Contact

Matt Stern
mstern@downers.us
Staff Engineer
(630) 434-5463

Project Summary

This project involves storm sewer improvements on Grant Street from Fairview Ave to Florence Avenue, Florence Avenue from Grant Street to Otis Avenue and on Otis Avenue west of Florence Avenue. Restoration will include street resurfacing and sidewalk improvements at intersections.

 

    Click Here to View this Project on the Construction Updates Interactive Map

 

Project Alerts

Public Meeting 6/16/2022 @ 6pm at 5101 Walnut Ave

Recent Progress

11/18/22

Punch list work is complete. Project is complete.

11/11/22

Project is substantially complete. Contractor is expected to complete punch list work by the end of next week, weather pending.

11/04/22

Project is substantially complete. Contractor is expected to complete punch list work over the course of the next week, weather pending.

10/28/22

Roadway paving is complete. Restoration work is expected to continue into next week, weather pending.

10/21/22

Road patching is complete. Resurfacing is expected to take place the week of 10/24, weather pending.

10/14/22

  • Concrete curb and gutter, sidewalk, and driveway work is complete. Residents are advised to keep vehicles off of new concrete for 7-10 days to allow concrete to harden.
  • Asphalt work is expected to begin the week of 10/17, weather pending.

10/07/22

  • Underground work is expected to be completed by next week.
  • Concrete curb and gutter work is expected to begin next week, weather pending. Residents who will temporarily lose driveway access will receive a door hanger notification as well as a knock on the door prior to work starting.

9/30/22

Underground work is expected to continue next week, weather pending.

9/23/22

Underground work is expected to continue next week, weather pending.

9/16/22

Underground work is expected to continue next week, weather pending.

9/9/22

Work is expected to take place the week of 9/12, weather permitting.

9/2/22

Work is expected to take place the week of 9/5, weather permitting.

8/26/22