Skip to main content

Linden Drainage Improvements

 

Table #: Project completion and contact information.
Project InformationData
Project # SW-08017(K)
Category Drainage
Start Date June 2019
End Date August 2019
Project Status

               Green
(Project is on schedule.)       

Village Contact

Katherine Zirbel, Staff Engineer II (630) 434-5488

Project Summary

The project includes installation and upgrading of storm sewer on Linden Place, between Chicago Avenue and Austin Street, and adjacent to Linden Place on small sections of Stanley Avenue, Chicago Avenue, Gierz Street, Prairie Avenue, Wilson Street, Franklin Street, and Austin Street. The project also includes reconstruction (including installation of concrete gutter) of Linden Place between Chicago Avenue and Austin Street, installation and upgrading of drinking water pipes on Linden Place between Chicago Avenue and Prairie Avenue, and removal and replacement of impacted pavement, driveway aprons, landscaping, and sidewalk.

Project Alerts

 

Recent Progress

7/19/19

Last week the contractor completed the installation of the storm sewer on Chicago Ave between Stanley Ave and Linden Pl. Next week the contractor is expected to continue working on storm sewer installation on Frankling St at Stanley Ave, and progress north on Linden Pl from Franklin St towards Wilson St.

7/12/19

The contractor has installed new storm sewer and removed the old drinking water pipes on Linden Place between Gierz Street and Prairie Avenue. Next week the contractor is expected to complete the storm sewer installation on Prairie Avenue between Stanley Avenue and Linden Place, as well as install the storm sewer on Chicago Avenue between Stanley Avenue and Linden Place. The contractor is then expected to start installing storm sewer on Franklin Street between Stanley Avenue and Linden Place.

7/5/19

The new watermain has been successfully installed and houses connected to it. During the upcoming week, the contractor is expected to install storm sewer on Linden Place starting at the Prairie Avenue intersection, and working northward towards Gierz Street.

6/28/19

During the first week of July, the contractor is expected to complete the installation of the new watermain, and to continue to prepare for the start of the storm sewer installation.

6/21/19

The contractor is expected to continue watermain installation and prepare for storm sewer installation during the week of June 24, 2019.

6/14/19

The contractor is expected to mobilize equipment and begin watermain installation between Prairie Ave. & Chicago Ave. the week of June 17, 2019.

6/3/19

The contractor is expected to prepare the site for construction this week, and begin construction the week of June 10, 2019.