Indianapolis Avenue Cross Street Drendel Road Drainage/Road/Sidewalk Improvements

 

Table #: Project completion and contact information.
Project InformationData
Project #

SW-087-19

Category Drainage
Start Date August/September 2019
End Date May 2020
Project Status

               
            Project is Complete              

Village Contact

Jim Tock, Engineering Manager (630) 434-2453

Project Summary

The proposed improvements include installation of a new storm sewer system that will provide the recommended level of service on Indianapolis Avenue from Drendel Road to Cross Street. The new storm sewer system on Indianapolis Avenue will connect to the recently completed Drendel Road storm sewer system, and will also facilitate future drainage improvements on Cross Street south of Ogden Ave. Indanapolis Avenue will be reconstructed and widened.

The proposed improvements also include reconstruction and reconfiguration of the Cross Street “s-curve” to improve pavement width and turning radii, installation of new sidewalk on Cross Street from Ogden Avenue to and through the Cross Street “s-curve”, and resurfacing of Drendel Road from Ogden Avenue to Indianapolis Avenue and Cross Street from Ogden Avenue to the Cross Street “s-curve.”

Project Alerts

 

Recent Progress

5/22/20

This week, the contractor completed sod restoration and retaining wall installation. The project is complete. Staff is working with the contractor to address punch list items.

05/15/20

This week, the contractor continued turf restoration and began retaining wall installation. Next week, the contractor is expected to complete turf restoration and retaining wall installation, and continue with minor items throughout the site.

05/08/20

This week, the contractor completed installation of the stone shoulders and began turf restoration activities. Next week, the contractor is expected to continue turf restoration and begin installation of retaining walls in two locations on Cross St.

05/01/20

Work this week was delayed by weather. Next week, the contractor is expected to install stone shoulders throughout the project and install retaining walls in two locations on Cross St.

4/24/20

This week, the contractor completed paving operations which included; milling, patching, and placement of the final surface layer of asphalt. Next week, the contractor is expected to install stone shoulders throughout the project and install retaining walls in two locations on Cross St.

4/17/20

The contractor is expected to begin grinding the road surface on Drendel, Cross, and Indianapolis, Monday, April 20th. This will be followed by road patching.

4/10/20

Next week, the contractor is expected to mobilize to begin grinding of the road surface on Drendel, Cross, and Indianapolis.

3/20/20

Last week and this week, the contractor mobilized to perform minor storm sewer items. At this time: resurfacing of Cross St from Ogden Ave to the s-curve, resurfacing of Drendel Rd from Ogden Ave to Indianapolis Ave, and placement of the final layer of asphalt on Indianapolis Ave and on Cross St through the s-curve, is exected to be completed in April/May.

12/20/19

This week, the contractor completed parkway restoration and demobilized from the site. Resurfacing of Cross St from Ogden Ave to the s-curve, and Drendel Rd from Ogden Ave to Indianapolis Ave, and placement of the final layer of asphalt on Indianapolis Ave and on Cross St through the s-curve will be performed in spring 2020.

Cross St at the ""s-curve"" (between Indianapolis Ave and Haddow Ave) has been opened to through traffic. All traffic restrictions have been removed.

12/13/19

This week, the contractor completed asphalt driveway restoration and continued parkway restoration. Next week, the contractor is expected to complete parkway restoration.

Due to the 14-day weather outlook, the final layer of asphalt on Indianapolis Ave and on Cross St through the s-curve will not be placed until spring 2020. Resurfacing of Cross St from Ogden Ave to the s-curve, and Drendel Rd from Ogden Ave to Indianapolis Ave, will also be postponed to spring 2020.

Cross St at the ""s-curve"" (between Indianapolis Ave and Haddow Ave) remains closed to through traffic. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page."

12/06/19

This week, the contractor completed new sidewalk installation, completed concrete driveway restoration, and began parkway restoration. Next week, the contractor is expected to restore asphalt driveways and place the final surface layer of asphalt on Indianapolis Ave and on Cross St at the s-curve.

At this time, we expect 100% project completion this year. However, depending on weather pattern the next few weeks, resurfacing of Cross St from Ogden Ave to the s-curve and Drendel Rd from Ogden Ave to Indianapolis Ave may take place spring 2020.

Cross St at the "s-curve" (between Indianapolis Ave and Haddow Ave) remains closed to through traffic. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page.

11/29/19

This week, the contractor continued installation of new sidewalk on Cross St and Indianapolis Ave. Next week, the contractor is expected to continue sidewalk installation, including sidewalk through driveways. Residents directly impacted by sidewalk installation will receive further notice.

At this time, we expect 100% project completion this year. However, depending on weather pattern the next few weeks, resurfacing of Cross St from Ogden Ave to the s-curve, and Drendel Rd from Ogden Ave to Indianapolis Ave may take place spring 2020.

Cross St at the ""s-curve"" (between Indianapolis Ave and Haddow Ave) remains closed to through traffic. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page."

11/22/19

This week, the contractor continued installation of new sidewalk on Cross St and Indianapolis Ave. Next week, the contractor is expected to continue sidewalk installation. Residents directly impacted by sidewalk installation will receive further notice.

At this time, we expect 100% project completion this year. However, depending on weather pattern the next few weeks, resurfacing of Cross St from Ogden Ave to the s-curve, and Drendel Rd from Ogden Ave to Indianapolis Ave, may take place spring 2020.

Cross St at the "s-curve" (between Indianapolis Ave and Haddow Ave) remains closed to through traffic. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page.

11/15/19

This week, the contractor began installation of new sidewalk on Cross St and Indianapolis Ave. Next week, the contractor is expected to continue sidewalk installation and continue placement of asphalt, weather pending.

Cross St at the "s-curve" (between Indianapolis Ave and Haddow Ave) remains closed to through traffic. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page.

11/08/19

This week, the contractor placed the first layer of asphalt at Indianapolis Ave and the Cross St "s-curve." Next week, the contractor is expected to install new sidewalk at Indianapolis Ave and on Cross St. Residents directly impacted by sidewalk installation will receive further notice.

Cross St at the "s-curve" (between Indianapolis Ave and Haddow Ave) remains closed to through traffic. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page.

11/01/19

Work this week has been delayed by weather. This week, the contractor began placement of curb and gutter at the Cross St "s-curve."

Next week, the contractor is expected to begain placement of asphalt at Indianapolis Ave and the Cross St "s-curve," followed by sidewalk installation. Residents directly impacted by sidewalk installation will receive further notice.

Cross St at the "s-curve" (between Indianapolis Ave and Haddow Ave) remains closed to through traffic. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page.

10/25/19

This week, the contractor began road reconstruction on Indianapolis Ave and on Cross St at the "s-curve." Next week, the contrator is expected to construct curb and gutter at the Cross St "s-curve" and place asphalt at Indianapolis Ave and the Cross St "s-curve." Cross St at the "s-curve" (between Indianapolis Ave and Haddow Ave) remains closed to through traffic. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page.

10/18/19

This week, the contractor performed construction layout for road reconstructions on Indianapolis Ave and on Cross St at the "s-curve." The contractor is expected to begin road reconstruction on Indianapolis Ave and on Cross St next week. Residents directly impacted by the road reconstruction work will be given further notice. Cross St at the "s-curve" (between Indianapolis Ave and Haddow Ave) will be closed to through traffic starting Monday, October 21, 2019. This section of Cross St will remain closed for 4 to 5 weeks. North-south traffic can use Belmont Rd or Walnut Ave. Please follow construction signage. Updates to the road closure will be posted on this construction update page.

10/11/19

This week, the contractor completed storm sewer installation on Cross St and tree removal throughout the site. The contractor is expected to begin road reconstruction on Indianapolis Ave and on Cross St the week of October 21st. Residents directly impacted by the road reconstruction work will be given further notice. Cross St at the "s-curve" (between Indianapolis St and Haddow Ave) will be closed to all traffic when road reconstruction begins. Updates to the road closure will be posted on this construction update page.

10/04/19

This week, the contractor completed storm sewer installation on Indianapolis Ave and began storm sewer installation on Cross St.

Next week, the contractor is expected to complete storm sewer installation on Cross St and begin road reconstruction on Indianapolis Ave.

9/27/19

This week, the contractor began installing storm sewer on Indianapolis Ave. Next week, the contractor is expected to continue storm sewer installation on Indianapolis Ave, and begin culvert installation on Cross St.

9/20/19

The contrator is expected to mobilize and begin installation of the storm sewer system on Indianapolis next week.

8/30/19

The contract was approved on the August 13, 2019 Council Agenda. A pre-construction meeting will be scheduled in the coming weeks. Construction notices will be sent to impacted residents prior to the start of construction.

8/2/19

Bids were opened and read on July 19, 2019. The contract will be going to council August 6th for first read, and August 13th for approval. Construction is expected to begin late August/early September.