Skip to main content

Hitchcock Avenue Drainage Improvements (Area 12)

 

Table #: Project completion and contact information.
Project InformationData
Project #

SW-08017L

Category Drainage
Start Date September, 2018
End Date November, 2018
Project Status

               Green
(Project is on schedule.)               

Village Contact

Jim Tock, Engineering Manager (630) 434-2453

Project Summary

The proposed improvements include installation of a new storm sewer system on private property north of Hitchcock Ave and an upgraded storm sewer system on Warren Ave from Woodward Ave to Cornell Ave. The new storm sewer system will intercept stormwater runoff at the areas identified and adequately convey it to the existing storm sewer system on Warren Ave at Woodward Ave. The proposed improvements will also provide connection points for future, private drainage improvements via the Stormwater Cost-Share Program.

 

Project Alerts

 

Recent Progress

11/16/2018

Pavement patching has been completed and the contractor has begun turf restoration and ditchline regrading.

11/2/2018

This week

The contractor has completed the storm sewer installation on Warren Avenue with the exception of the extension that will be installed south across the BNSF Right-of-Way to Hitchcock Avenue. The south extension across the BNSF Right-of-Way is awaiting approval from BNSF to complete the work. The contractor began pavement patching on Warren between Stonewall and Cornell.

Next week

The contractor will be working on the pavement patching on Warren between Woodward and Stonewall and parkway restoration.

10/26/2018

Contractor has completed the mainline storm sewer installation on Warren and Stonewall and will continue storm sewer installation across Warren next week.

10/12/2018

Contractor has begun storm sewer installation on Warren and will continue storm sewer installation on Warren next week.

10/5/2018

Contractor is expected to begin exploration of existing utilities and storm sewer installation on Warren Ave next week.

8/24/2018

Project expected to be awarded in early September 2018.

8/10/2018

Bidding for this project is currently underway.