Forest Avenue and Prince Street Drainage Improvements (Area 10)
Project Information | Data | ||
---|---|---|---|
Project # |
SW-08017J |
||
Category | Drainage | ||
Start Date | July, 2018 | ||
End Date | September, 2018 | ||
Project Status |
|
||
Village Contact |
Susan Quasney, Staff Engineer (630) 434-5564 |
Project Summary
Project Alerts
Recent Progress
10/12/2018
This week
Contractor has almost completed the new storm sewer line on Forest. All repairs and sanitary lines are anticipated to be complete by the end of this week.
Next week
Due to the complexities of the area, the backyard pipe through 4820 Forest has been removed from the contract. We anticipate all storm water work to be completed next week with restoration of the street to follow.
10/5/2018
This week
The contractor has completed the main storm sewer line installation along Franklin and is now heading north on Forest. Forest work will be slower due to utility line conflicts and lateral work, and is anticipated to be through most of next week.
Next week
Inlet work on Prince has begun, and inlet work on Prairie is anticipated for upcoming week. Temporary blockages of driveways and street closures will occur as required, but access will be restored by the end of each work day.
9/28/2018
Contractor expected to mobilize on Wednesday, September 26 or Thursday, September 27. Work will begin with investigatory digging to locate utilities. Temporary lane closures may occur periodically.
8/24/2018
Project expected to be awarded in early September 2018.
8/10/2018
Bidding for this project is currently underway.