Drendel Road Drainage Improvements (Area 7)

 

Table #: Project completion and contact information.
Project InformationData
Project #

SW-08017G

Category Drainage
Start Date September, 2018
End Date November, 2018
Project Status

               Green
(Project is on schedule.)               

Village Contact

Jim Tock, Engineering Manager (630) 434-2453

Project Summary

The proposed improvements include installation of a new storm sewer system on Drendel Rd from just north of Indianapolis Ave to the dead end near the Belmont Prairie, along the Prairie Ave right-of-way east to Cross St and on Cross St from just north of the "S-Curve" to Haddow Ave. The project will also include road improvements and installation of new sidewalk. Please see project location map on this page. The new storm sewer system will intercept stormwater runoff at the areas identified and adequately convey it to the existing storm sewer system on Cross St at Haddow Ave. The proposed improvements will also provide connection points for future, private drainage improvements via the Stormwater Cost-Share Program.

 

Project Alerts

Cross St at the "s-curve" (between Indianapolis St and Haddow Ave) will remain closed to through traffic until mid-November.  North-south traffic can use Belmont Rd or Walnut Ave.  Please follow construction signage.  Updates to the road closure will be posted on this construction update page.

The contractor is expected to continue working on Saturdays to keep the project on track for November completion.

Recent Progress

12/14/2018

Due to current weather conditions, the final layer of asphalt (surface) is expected to be placed in early spring. Excavation of ditches and restoration of parkways with topsoil and sod is underway. Sod is no longer available for 2018. Seed and blanket is being used for parkway restoration. Contractor will also be onsite the next couple weeks completing miscellaneous items.

12/7/2018

Asphalt patching throughout the project is complete. Asphalt and concrete driveway restoration throughout the project is complete. Due to current weather conditions, the final layer of asphalt (surface) is expected to be placed in early spring. Excavation of ditches and restoration of parkways with topsoil and sod is underway. Sod is limited at this time. If sod becomes unavailable, seed and blanket will be used. Contractor will also be onsite the next couple weeks completing miscellaneous items.

11/30/2018

This week

Road patching and placement of the first asphalt layer is complete on Drendel south of Indianapolis and on Cross south of the s-curve. The final layer of asphalt cannot be placed in these areas until we experience warmer temperatures. Restoration of asphalt driveways on Drendel and Cross is complete.

Next week

The contractor is expected to complete road patching on Drendel north of Indianapolis and on Cross through and north of the s-curve and restore all impacted concrete driveways. Sod restoration will also take place, weather-pending.

11/23/2018

This week

Placement of concrete gutter and new sidewalk on Cross is complete. Road patching is underway throughout the site. Road milling on Drendel south of Indianapolis and on Cross south of the s-curve is underway on both Drendel and Cross.

Next week

Next week, the contractor is expected to complete road patching and begin placing new layers of asphalt surface on both Cross and Drendel.

11/16/2018

This week

The first layer of asphalt has been placed for the road reconstructed portion of Drendel. New sidewalk installation on Drendel is complete. Placement of concrete gutter on the east side of Cross is complete. Excavation for concrete curb and gutter and sidewalk on Cross is underway.

Next week

Next week, the contractor is expected to complete concrete curb and gutter and sidewalk installation on Cross and begin asphalt patching on both Drendel and Cross. Weather permitting, the contractor will mill and resurface Drendel south of Indianapolis and Cross south of the s-curve. Measures will be taken to restore the site as much as possible before Thanksgiving weekend.

11/9/2018

This week

All storm sewer on both Cross and Drendel is complete. Road reconstruction and excavation for sidewalk on Drendel is underway. Excavation for curb and gutter and sidewalk on Cross is underway.

Next week

The contractor is expected to complete concrete curb and gutter and sidewalk installation on Drendel and Cross as well as continue road reconstruction on Drendel.

11/2/2018

This week

Contractor has continued open-trench storm sewer on Cross from Haddow to north of the s-curve.

Next week

The contractor is expected to complete storm sewer installation on Cross and begin road reconstruction on Drendel and curb and gutter installation on Cross between Haddow and the s-curve.

10/26/2018

This week

Contractor completed open-trench storm sewer installation on Drendel, completed installation of the trenchless (directionally drilled) storm sewer within the Prairie Ave right-of-way from Drendel to Cross and began installation of open-trench storm sewer on Cross at Haddow, moving north towards the s-curve.

Next week

The contractor is expected to continue open-trench storm sewer installation on Cross.

10/19/2018

This week

Contractor continued storm open-trench sewer installation on Drendel and began and completed installation of the trenchless (directionally drilled) storm sewer within the Prairie Ave right-of-way from Drendel to Cross.

Next week

The contractor is expected to complete open-trench storm sewer installation on Drendel and begin open-trench storm sewer installation on Cross.

10/12/2018

This week

Contractor continued storm open-trench sewer installation on Drendel and installed trenchless (directionally drilled) storm sewer on Cross.

Next week

Next week, the contractor is expected to complete open-trench storm sewer installation on Drendel, begin open-trench storm sewer installation on Cross and begin trenchless (directionally drilled) storm sewer installation within the Prairie Ave right-of-way from Drendel to Cross.

10/5/2018

This week

Contractor continued storm sewer installation on Drendel south of Indianapolis and drilling/excavation for trenchless (directionally drilled) storm sewer installation on Cross at and south of the s-curve.

Next week

Installation of storm sewer pipe on Drendel and on Cross is expected to continue next week. Drilling/excavation for the trenchless (directionally drilled) storm sewer installation within the Prairie Ave right-of-way north of the Belmont Prairie is expected to begin next week. Cross St at the s-curve is still closed to through traffic.

9/28/2018

This week

Contractor has begun storm sewer installation on Drendel south of Indianapolis and excavation for trenchless (directionally drilled) storm sewer installation on Cross at the s-curve. Cross St at the s-curve is now closed to through traffic.

Next week

Installation of storm sewer pipe on Drendel and on Cross is expected to continue.

9/21/2018

Contractor is expected to mobilize to the site the week of 9/24/18. Cross St at the "s-curve" (between Indianapolis St and Haddow Ave) will be closed to all traffic starting Thursday, September 27, 2018. The closure is expected to last up to 5 weeks. Updates to the road closure will be posted on this construction update page.

9/14/2018

Contractor is expected to mobilize to the site the week of 9/24/18.

9/7/2018

Contractor is expected to mobilize to the site the week of 9/17/18.

8/24/2018

Construction contract awarded at August 21, 2018 Council Meeting. Pre-construction work underway.

8/3/2018

Project expected to be awarded in August 2018.

7/13/2018

The bidding for this project is currently underway.