Table #: Project completion and contact information.
Project InformationData
Project # SW-08017A
Category Drainage
Start Date September, 2018
End Date October, 2018
Project Status

               Green
(Project is on schedule.)              

Village Contact

Jim Tock, Engineering Manager (630) 434-2453

Project Summary

The proposed improvements include installation of a ditch and/or storm sewer on private property west of Highland Ave and east of Saratoga Ave between Black Oak Dr and Candlwood Dr and upgrading storm sewer system on Candlewood Ct south of Black Oak Dr. The new storm sewer system will intercept stormwater runoff at the areas identified and adequately convey it to the existing storm sewer system in the rear yards east of Saratoga Ave between Black Oak Dr and Candlewood Dr. The proposed improvements will also provide connection points for future, private drainage improvements via the Stormwater Cost-Share Program.

 

Project Alerts

 

Recent Progress

10/26/2018

Sod restoration is complete. Staff is working with contractor to wrap up miscellaneous punch list items.

10/19/2018

This week

The contractor placed topsoil. 

Next week

Sod is expected to be placed next week. 

10/12/2018

Brick driveway restoration is complete. Sod placement has been delayed due to weather and is expected to take place next week.

10/5/2018

This week

Restoration of impacted road and curb and gutter is complete.

Next week

Brick driveway and sod restoration is expected to be completed next week.

9/28/2018

Restoration of impacted road and curb and gutter is underway and is expected to continue next week, followed by sod restoration.

9/21/2018

Contractor has completed storm sewer installation on Candlewood Ct/Dr. Restoration of impacted road and curb and gutter is underway and is expected to continue next week.

9/14/2018

This week

Contractor has begun installing storm sewer.

Next week

The contractor is expected to continue storm sewer installation next week. 

9/7/2018

This week

Contractor has installed tree protection fence and has begun exploration of existing utilities.

Next week

Contractor is expected to begin storm sewer installation next week.

8/31/2018

Contractor is expected to begin site preparation work, i.e. tree protection fence and exploratory digging next week, with storm sewer installation scheduled to begin the week of 9/10/18.

8/24/2018

Construction contract awarded at August 21, 2018 Council Meeting. Pre-construction work underway.

8/3/2018

Project expected to be awarded in August 2018.

7/13/2018

The bidding for this project is currently underway.