Barneswood and Saratoga Culvert Pipe Replacements

 

Table #: Project completion and contact information.
Project InformationData
Project # SW-070
Category Drainage
Start Date April 2019
End Date June 2019
Project Status

               Green
(Project is on schedule.)

Village Contact

Jim Tock, Engineering Manager (630) 434-2453

Project Summary

This project includes culvert pipe and headwall replacement on Barneswood Dr between Creekwood Ct and Quince Ct and culvert pipe replacement on Saratoga Ave between Brookside Ln and Black Oak Dr.

 

Project Alerts

 

Recent Progress

7/19/19

Barneswood: The contractor is expected to complete minor work with the creek near the north headwall next week.

Saratoga: Pipe joint repair of existing storm sewer pipe west of Saratoga is expected to take place in August. This work will take place inside the pipe.

7/12/19

Barneswood: Handrail installation is complete.

Saratoga: Pipe joint repair of existing storm sewer pipe west of Saratoga is expected to take place in August. This work will take place inside the pipe.

7/5/19

Barneswood: Handrail installation is expected to take place next week.

Saratoga: Pipe joint repair of existing storm sewer pipe west of Saratoga is expected to take place in August. This work will take place inside the pipe.

6/28/19

Barneswood: Turf restoration is complete. Handrail installation is expected to take place next week.

Saratoga: Turf restoration is complete.

6/21/19

Barneswood: Turf restoration is expected to take place next week, weather pending.

Saratoga: Turf restoration is expected to take place next week, weather pending.

6/14/19

Barneswood: Sidewalk, curb and gutter, and pavement restoration is complete. Turf restoration is underway and expected to be completed next week, weather pending.

Saratoga: Turf restoration is expected to take place next week, weather pending.

6/7/19

Barneswood: Culvert pipe and concrete headwall installation have been completed. Sidewalk, curb and gutter, pavement, and turf restoration are underway and expected to be completed next week, weather pending.

Saratoga: Turf restoration is expected to take place next week, weather pending.

5/31/19

Barneswood: The utility conflict that has been delaying this portion of the project was resolved Wednesday, 5/29/19; however, work is still being delayed by recent rain. Once creek elevations recede, culvert pipe installation will continue. We expect three to five working days to complete the work within the creek.

Saratoga: The contractor completed sidewalk, curb and gutter, and pavement restoration. Turf restoration is expected to take place next week, weather pending.

5/24/19

Barneswood: Work has been delayed by a utility conflict and by recent rain. Once the utility conflict is resolved, culvert pipe installation will continue.

Saratoga: The contractor has begun sidewalk, curb and gutter, and pavement restoration. This work is expected to be completed next week.

5/17/19

Barneswood: Work has been delayed by a utility conflict and by recent rain. The utility conflict is expected to be resolved by early next week, at which point culvert pipe installation will continue.

Saratoga: Installation of the culvert pipe is complete. Saratoga is now open to through traffic, although during construction hours, one lane may be closed. Next week, the contractor is expected to begin restoration of curb and gutter, sidewalk and asphalt.

5/10/19

Barneswood: Work has been delayed by utility conflict and by recent rain. Communication with the utility company is ongoing.

Saratoga: Work is expected to continue Monday, 5/13/19, weather pending. Saratoga will continue to be closed to through traffic until culvert pipe replacement is complete. Please follow all construction signage.

5/3/19

Barneswood: Work has been delayed by utility conflict and by recent rain. Communication with the utility company is ongoing.

Saratoga: Culvert pipe replacement began 4/26/19 and has since been delayed by recent rain. Work is expected to continue when water elevations within the creek recede. Saratoga was closed to through traffic on 4/26/19 and will continue to be closed until culvert pipe replacement is complete. Please follow all construction signage.

4/19/19

Barneswood: The contractor returned to the site on Monday, but further work has been delayed by utility conflict. Communication with the utility is ongoing.

Saratoga: The start of site preparation has been delayed by the completion of the Barneswood location. The contractor is expected to begin site preparation work and potentially culvert pipe replacement next week, weather pending. Saratoga may be closed to through traffic at the end of next week. Please follow all construction signage.

4/12/19

Barneswood: This week, the contractor continued culvert pipe and concrete headwall replacement. Work was delayed by rain and conflicts with utilities. The contractor is expected to complete culvert pipe and headwall replacement next week, weather-pending.

Saratoga: The start of site preparation has been delayed by the completion of the Barneswood location. The contractor is expected to begin site preparation work and potentially culvert pipe replacement next week, weather pending. Saratoga may be closed to through traffic at the end of next week. Please follow all construction signage.

4/5/2019

Barneswood: The contractor has begun culvert pipe removal and replacement on the south side of Barneswood. Concrete headwall replacement on the south side is underway. The contractor is expected to complete culvert pipe and headwall replacement next week, weather-pending.

Saratoga: The contractor is expected to begin site preparation work next week, with culvert pipe replacement expected to begin the week of Monday, April 15, 2019. Saratoga will remain open to through traffic next week but will be closed starting Monday, April 15, 2019. This schedule is weather-pending.

3/29/2019

The contractor is expected to begin site preparation and mobilization for the Barneswood Drive site Monday, April 1, 2019, weather pending.

Barneswood Drive will be closed to through traffic starting Monday, April 1, 2019. Please follow all construction signage. Additional notification will be given to residents as needed.

3/15/2019

The contractor will begin site preparation and mobilization as early as Monday, April 1, 2019. The contractor is expected to begin construction at the Barneswood Avenue site first, followed by construction at the Saratoga Avenue site. Barneswood Drive and Saratoga Avenue will be closed to all traffic for portions of the project. Please follow all construction signage. Additional notification will be given to residents as needed.