Skip to main content

2022 Williams Street Watermain

 

Project InformationData
Project # WA-040
Category Water
Start Date May-June 2022
End Date June-July 2022
Project Status

On Schedule

Village Contact

Design & Construction:

Scott Vasko, Engineering Manager, 630-434-6804

Residential Service Connections:

David Moody, Assistant Director of Public Works - Operations,  630-434-5474

Project Summary

Extension of watermain from 41st Street to Ogden Avenue.

     Click Here to View this Project on the Construction Updates Interactive Map

Project Alerts

Resident meeting regarding this project was held 09/28/21

  • Last day to submit plumbing permit/connection fees: APRIL 15, 2022
  • Last day to complete residential work: OCTOBER 31, 2022

Project Documents

Recent Progress

9/2/22

Parkway restoration was completed from 41st to Ogden. The Village's contractor will complete restoration from 41st to 39th within the next few weeks.

8/5/22

All roadway patching was completed last week. Parkway restoration will be completed later in the year when temperatures are lower.

7/22/22

All water main work is completed. Patching of Wiliams north of 41st will be completed at a later date once construction materials becomes available.

7/15/22

The contractor completed pavement patching on Williams between 41st and Ogden. Patching of Wiliams north of 41st will be completed at a later date.

7/8/22

The contractor completed curb replacement this week. The contractor is scheduled to complete pavement patching on Williams between 41st and Ogden next week.

7/1/22

The contractor is scheduled to complete curb restoration and pavement patching on Williams between 41st and Ogden next week.

6/24/22

The contractor installed all water services on Williams from Ogden to 39th Street. Next week the contractor may begin concrete restoration on Williams between 41st and Ogden.

6/17/22

The contractor is waiting for testing and chlorination results before starting on water services. The contractor is scheduled to start water services in the near future.

6/10/22

The contractor installed water main on Williams from 41st to Ogden this week. The contractor is scheduled to begin testing and chlorination next week on Williams from 41st to Ogden.

6/3/22

The contractor installed tree protection on Williams and delivered equipment this week. Next week the contractor is scheduled to start water main installation on Williams.

5/13/22

The preconstruction meeting was held last week and the project is scheduled to start the week after Memorial Day.

03/25/22

This project was advertised on March 25, 2022. Bids will be opened in April and the project is scheduled to go to council for approval in May.