2022 Pavement Striping Maintenance

 

Table #: Project completion and contact information.
Project InformationData
Project # TR-023
Category Traffic
Start Date April 2022
End Date May 2022
Project Status Complete
Village Contact

Michael Tuman, Transportation Manager
mtuman@downers.us
(630) 434-6863

Project Summary

This provject involves restoring pavement markings at various locations on the concrete pavement in the Downtown Business District (DBD).

 

     Click Here to View this Project on the Construction Updates Interactive Map

Project Alerts


Recent Progress

6/17/22

Project was completed on 6/16.

6/10/22

Contractor has begun restriping on various roads. Moinvg lane closures can be expected during thier operatiosn whic will have minor impacts to traffic.

4/22/22

Work was completed on 4/15. This project is now complete.

4/15/22

Downtown striping work took place on 4/12, 4/14, and 4/15. Work will be complete by the end of the week, 4/15.

4/8/22

Rain has delayed this work. It is now expected to take place the week of April 11, weather permitting.

4/1/22

Work is expected to take place the week of April 4th, weather permitting.

03/25/22

Work is expected to take place the week of April 4th, weather permitting.