Skip to main content

2022 Lyman & 62nd Drainage Improvements

 

Project InformationData
Project # SW-086-20C
Category Drainage
Start Date July 2022
End Date October 2022
Project Status

On Schedule

Village Contact

Matt Stern, Staff Engineer

mstern@downers.us

630-434-5463

Project Summary

This project involves storm sewer improvements on 62nd Street between Washington Street and Lyman Ave. This project also involves new storm sewer installation on Lyman Ave between 61st Street and 63rd Street, and new curb & gutter. Restoration will include street resurfacing, sidewalk improvements at intersections, parkway regrading, and driveway replacements.

     Click Here to View this Project on the Construction Updates Interactive Map

Pre Construction Updates

Public Meeting 3/10/2022 @ 6pm at 5101 Walnut Ave


Project Alerts

 

Recent Progress

11/18/22

Contractor is expected to complete punch list work next week, weather pending.

11/11/22

Contractor is expected to complete restoration and punch list work next week, weather pending.

11/04/22

Paving work is complete. Contractor is expected to complete restoration work over the course of the next week, weather pending.

10/28/22

Concrete work is complete. Roadway milling and resurfacing work is expecting to continue into next week, weather pending.

10/21/22

Concrete work has been delayed slightly by material shortages. Concrete curb and gutter, sidewalk, and driveway work is expected to continue next week, weather pending. After concrete work is complete asphalt resurfacing will begin.

10/14/22

  • Concrete curb and gutter, sidewalk, and driveway work is complete. Residents are advised to keep vehicles off of new concrete for 7-10 days to allow concrete to harden.
  • Asphalt work is expected to begin the week of 10/17, weather pending.

10/07/22

  • Work has resumed after bypassing the utility conflict in the intersection. All underground work has been completed.
  • Concrete curb and gutter work is expected to begin next week, weather pending. Residents who will temporarily lose driveway access will receive a door hanger notification as well as a knock on the door prior to work starting.

9/30/22

Work is expected to continue next week after resolution of a utility conflict, weather pending.

9/23/22

Work is expected to continue next week after resolution of a utility conflict, weather pending.

9/16/22

Work is expected to continue next week after resolution of a utility conflict, weather pending.

9/9/22

Work is expected to continue next week after resolution of a utility conflict, weather pending.

9/2/22

Underground work is expected to continue into next week, weather pending. After underground work is complete, curb and pavement replacement will begin.

8/26/22

Underground work is expected to continue into next week, weather pending.

8/19/22

Underground work is expected to begin the week of 8/22, weather pending.

8/12/22

Underground work is expected to begin the week of 8/15, weather pending.