Table #: Project completion and contact information.
Project InformationData
Project # ST-004D
Category Streets 
Start Date September 2022
End Date October 2022
Project Status Complete
Village Contact

Stephanie Graves, Staff Engineer
sgraves@downers.us
(630) 434-5487

Project Summary

Annual patching program, consists of spot-pavement patching in locations throughout the city. If there are patching locations in your neighborhood, you will see signs go up in the parkway in the days leading up to the work to ensure no parking takes place in the work areas. Patches are excavated and repaved in the same day and opened back up to traffic afterwards.

Project Alerts

 

 

 

Recent Progress

10/07/22

Punch list/clean up items have been addressed. This is the last update for this project.

9/30/22

Village is awaiting completion of punch list/cleanup items.

9/23/22

Village is awaiting completion of punch list/cleanup items.

9/16/22

Village is awaiting completion of punch list/cleanup items.

9/9/22

Village is awaiting completion of punch list/cleanup items.

9/2/22

Village is awaiting completion of punch list/cleanup items.

8/26/22

A punch list was issued to address cleanup and other items.

8/19/22

Patching crews were in town the week of 8/15 to work on remaining locations. Following the completion of work, a punch list will be issued for miscellaneous cleanup and other items to address.

8/12/22

Remaining patching work is expected to be completed by the end of August. This schedule is subject to change.

8/5/22

Patching work on Williams was completed on Friday, 7/29. Patching for the remaining locations is expected to be completed by the end of August. This schedule is subject to change.

7/29/22

A patching crew is expected to complete the Williams St work within the next two weeks. At this time, all remaining patching locations are expected to be completed by the end of August. This schedule is subject to change.

7/22/22

A preconstruction meeting will be scheduled within the next 2 weeks, at which time a schedule will be better established.

7/15/22

The contract was awarded at the July 12th Village Council meeting. A preconstruction meeting will be scheduled within the next 3 weeks, at which time a schedule will be better established.

7/1/22

Bids are under evaluation and will be presented to Village Council on July 12th.

6/24/22

Bids were opened on June 23 and are under evaluation.

6/17/22

Bids will be opened on June 23, 2022.

6/10/22

The project was advertised for bidding this week. Bids will be opened on June 23rd, 2022.