2022 Fairview Avenue Resurfacing

 

Table #: Project completion and contact information.
Project InformationData
Project # ST-059
Category Streets 
Start Date June 2022
End Date September 2022
Project Status Complete
Village Contact

Nate Hawk, Staff Engineer II
nhawk@downers.us
630-434-5467

Project Summary

This work will include the pavement resurfacing of Fairview Avenue from Ogden Avenue to Maple Avenue, and from 2nd Street to 8th Street. This includes the spot-repair of curb, sidewalk replacement for ADA compliance, grinding the existing top layer of asphalt, pavement patching as needed, and two new layers of asphalt with adjustments to utility structures as needed. This also includes parkway restoration in disturbed areas and new pavement striping.

     Click Here to View this Project on the Construction Updates Interactive Map

Project Alerts


Recent Progress

11/04/22

This week the contractor completed the punchlist items. The project is complete.

10/28/22

Village is awaiting completion of punch list/cleanup items.

10/21/22

Village is awaiting completion of punch list/cleanup items.

10/14/22

Village will issue punch list/cleanup items to the contractor and coordinate with contractor for completion.

10/07/22

This week the contractor completed HMA paving and pavement striping. Next week a punchlist will be issued to the contractor.

9/30/22

This week the contractor began restoration, completed pavement patching, and began utility frame and lid adjustments. Next week the contractor plans to pave HMA surface course and begin pavement striping.

9/23/22

This week the contractor completed replacement of detector loops for traffic signals affected by the surface removal. Next week the contractor plans to adjust utility frames and lids and begin paving HMA surface.

9/16/22

This week the contractor completed placement of the HMA level binder. Next week the contractor plans to work on detector loop replacements and may begin utility frame and lid adjustments.

9/9/22

This week the contractor completed the HMA surface removal. Next week the contractor plans to place level binder and begin utility frame and lid adjustments.

9/2/22

The contractor has lowered the structure frame and lids. Next week the contractor plans to begin HMA surface removal.

8/19/22

This week the contractor completed the curb and sidewalk installation on the west side of Fairview Avenue. The next step will be to begin lowering structure frames and lids to prepare for milling the pavement.

8/12/22

This week the contractor poured sidewalk and curb on the east side of Fairvew. Curb and sidewalk have been removed and sidewalk areas were prepared for concrete on the west side of Fairview. Next week the contractor plans to pour concrete curb and sidewalks on the west side of Fairview.

8/5/22

 

  • This week the contrator removed concrete and anticipates to begin pouring concrete curb on the east side of Fairview Avenue.
  • Next week the contractor plans to pour concrete sidewalks on the east side of Fairview Avenue, remove concrete and begin pouring concrete on the west side of Fairview Avenue.

 

7/15/22

Construction activities are on hold at this time due to lack of availability of construction materials.

7/8/22

Construction activities are on hold at this time due to lack of availability of construction materials.

7/1/22

Construction activities are on hold at this time due to lack of availability of construction materials.

6/24/22

Construction activities are on hold at this time due to lack of availability of construction materials.

6/17/22

This week the contractor sawcut concrete curb for removals. There is a delay in the schedule and no work planned for next week.

5/13/22

A preconstruction meeting took place on May 4th. The contractor is planning to begin work the week of June 13th, weather permitting.