2021 Watermain Replacement Contract A

 

Project InformationData
Project # WA-028
Category Water
Start Date May 2021
End Date October 2021
Project Status

On Schedule

Village Contact

Scott Vasko, Engineering Manager (630) 434-6804

 

Project Summary

The project will consist of the water main replacement on

 

The work will be completed in phases:

  1. Pavement removal and excavation
  2. Installation of main line water main
  3. Testing and chlorination of main line water main
  4. Connection of existing water service lines to new main line water main
  5. Pavement, concrete and turf restoration

Project Alerts

4/2/21

This project was advertised on March 31, 2021. Bids will be opened in April and the project is scheduled to go to council for approval in May.


 

Recent Progress