Skip to main content

2021 Springside Ave & Prentiss Creek Culvert Replacement

 

Table #: Project completion and contact information.
Project InformationData
Project # SW-070
Category Drainage
Start Date February 2021
End Date June 2021
Project Status On Schedule
Village Contact

Zlatko Nikolov, Staff Engineer (630) 434-5564

Project Summary

This project includes culvert pipe replacement where Prentiss Creek crosses Springside Ave (just north of Bolson Dr), storm sewer replacement, roadway and sidewalk replacement, installation of an ornamental fence adjacent to the sidewalk, and streambank stabilization. The work will require closure of Springside Ave and a detour route will be posted.

Project Alerts

 

Recent Progress

10/23/20

Due to the lead time on material required to complete the project, the project is now expected to begin in Spring 2021.

9/4/20

The construction contract was approved at the September 8th Council Meeting. A preconstruction meeting is planned for the week of September 14th. Construction notices will be sent out to those impacted by the project when a construction schedule is established.

8/28/20

Bids have been received. The construction contract is scheduled for Council approval in September.

8/14/20

The project is currently out to bid, with bids due 8/21/20.