Skip to main content

2021 Springside Ave & Prentiss Creek Culvert Replacement

 

Table #: Project completion and contact information.
Project InformationData
Project # SW-070
Category Drainage
Start Date April 2021
End Date July 2021
Project Status On Schedule
Village Contact

Zlatko Nikolov, Staff Engineer (630) 434-5564

Project Summary

This project includes culvert pipe replacement where Prentiss Creek crosses Springside Ave (just north of Bolson Dr), storm sewer replacement, roadway and sidewalk replacement, installation of an ornamental fence adjacent to the sidewalk, and streambank stabilization. The work will require closure of Springside Ave and a detour route will be posted.

Project Alerts

 

Recent Progress

4/16/21

Installation of the 66" storm sewer extension is expected to begin 4/16/21. Framing for the poured-in-place headwalls and wingwalls will continue. Road reopening delayed until further notice.

4/9/21

Installation of precast culvert sections has been completed. Framing for the poured-in-place headwalls and wingwalls will continue. Road reopening has been delayed.

4/2/21

Installation of precast culvert sections expected to be completed 4/2. Framing for the poured-in-place headwalls and wingwalls will take place early next week. Road reopening is expected to take place the second half of the week.

3/26/21

Precast pipes and structures were delivered on-site. East sidewalk is expected to be closed over the weekend. Road closed starting Monday, 3/29.

3/19/21

Tree removal is underway and is expected to be completed the week of 3/22. Road closure and construction is expected to begin 3/29.

03/12/21

Tree removal is expected to begin the week of 3/22/21.

10/23/20

Due to the lead time on material required to complete the project, the project is now expected to begin in Spring 2021.

9/4/20

The construction contract was approved at the September 8th Council Meeting. A preconstruction meeting is planned for the week of September 14th. Construction notices will be sent out to those impacted by the project when a construction schedule is established.

8/28/20

Bids have been received. The construction contract is scheduled for Council approval in September.

8/14/20

The project is currently out to bid, with bids due 8/21/20.