2021 Springside Ave & Prentiss Creek Culvert Replacement
Project Information | Data | |
---|---|---|
Project # | SW-070 | |
Category | Drainage | |
Start Date | February 2021 | |
End Date | June 2021 | |
Project Status | On Schedule | |
Village Contact |
Zlatko Nikolov, Staff Engineer (630) 434-5564 |
Project Summary
This project includes culvert pipe replacement where Prentiss Creek crosses Springside Ave (just north of Bolson Dr), storm sewer replacement, roadway and sidewalk replacement, installation of an ornamental fence adjacent to the sidewalk, and streambank stabilization. The work will require closure of Springside Ave and a detour route will be posted.
Project Alerts
Recent Progress
10/23/20
Due to the lead time on material required to complete the project, the project is now expected to begin in Spring 2021.
9/4/20
The construction contract was approved at the September 8th Council Meeting. A preconstruction meeting is planned for the week of September 14th. Construction notices will be sent out to those impacted by the project when a construction schedule is established.
8/28/20
Bids have been received. The construction contract is scheduled for Council approval in September.
8/14/20
The project is currently out to bid, with bids due 8/21/20.