2021 Sidewalk Replacement/Rehabilitation Program

Table #: Project completion and contact information.
Project InformationData
Project # S-006-20
Category Sidewalks
Start Date April 2021
End Date August 2021
Project Status On Schedule
Village Contact

Matthew Stern, Staff Engineer (630) 434-5463

Project Summary

This project provides for the rehabilitation of sections of sidewalk that have become vertically separated by saw cutting the lifted edge to provide a smooth walking surface.

Project Alerts

 

Recent Progress

4/16/21

Contractor is continuing work throughout the Village into next week, weather pending.

4/9/21

Contractor is continuing work throughout the Village into next week, weather pending.

4/2/21

Contractor is continuing work throughout the Village into next week, weather pending.

3/26/21

Contractor began work this week and will continue saw cutting sidewalks next week, weather pending.

3/19/21

Work is scheduled to being next week, 3/22, weather pending.

3/12/21

Rehab contract has been awarded. Contractor estimates start of work to be late next week, weather pending.