2020 Watermain Replacements (Contract B)

 

Project InformationData
Project # WA028
Category Water
Start Date August 2020
End Date October 2020
Project Status

               Green
(Project is on schedule.)

Village Contact

Scott Vasko, Staff Engineer (630) 434-6804


Project Summary

The project will consist of the water main replacement on Puffer Road from 61st Street to 63rd Street, Warren Avenue from Belmont Road to Cornell Avenue, and Florence Avenue from Foxfire Court to 41st Street. Work will also include patching of the existing roadway where the new water main will be installed, sidewalk improvements at the intersections and street resurfacing.

 

The work will be completed in phases:

  1. Pavement removal and excavation
  2. Installation of main line water main
  3. Testing and chlorination of main line water main
  4. Connection of existing water service lines to new main line water main
  5. Pavement, concrete and turf restoration

Project Alerts

 

Recent Progress

10/23/20

Contractor completed all water main work on Warren this week, and started parkway restoration on Puffer. Contractor is scheduled to finish all concrete work this week, or early next week depending on the weather. Contractor is scheduled to start asphalt work and continue parkway restoration on all streets next week depending on the weather.

10/16/20

Contractor completed all water main installation on Florence this week, and began water service installations on Warren. Contractor is scheduled to complete all water main work on Warren next week, and possibly install water services on Florence. Contractor may begin concrete restoration next week on Warren and Puffer.

10/09/20

Contractor completed all water service connections on Puffer this week. Contractor also completed all remaing water main work on Puffer, and removed all existing hydrants on Puffer. The contractor started water main installation on Florence between Florence and 41st.

Next week the contractor is scheduled to comlpete water main installation on Florence and begin water service installations on Warren.

10/2/20

Contractor completed water main installation on Warren this week and began testing of the water main on Warren. Contractor also started water service installations on Puffer this week. Contractor is scheduled to complete testing and chlorinating the new main on Warren next week. Contractor is also scheduled to continue water service installations on Puffer next week.

9/25/20

Contractor completed water main installation on Puffer this week and began testing and chlorinating of the water main on Puffer. Contractor started installation of water main on Warren. Next week contractor is scheduled to complete water main installation on Warren and begin water services on Puffer.

9/18/20

Contractor continued water main work on Puffer this week. Contractor is scheduled to complete main line water main on Puffer next week, and start water main installation on Warren. Contractor is scheculed to be testing new water main on Puffer next week.

9/11/20

Contractor started water main work on Puffer this week. Next week contractor will continue installing water main on Puffer.

9/4/20

This week the contractor dropped off equipment and completed construction layout and traffic control on Puffer. Next week, the contractor will begin water main installation on Puffer.

8/28/20

Work is scheduled to start on Puffer the week of August 31st.

8/14/20

Work is scheduled to start on Puffer the week of August 24th.

8/7/20

A preconstruction meeting was held this week. Work is scheduled to start the week of August 17th or 24th..

7/31/20

A preconstruction meeting is scheduled for next week. Work is scheduled to start the week of August 10th.

7/24/20

The contract was awarded at the July 21, 2020 council meeting. Work is scheduled to start in August.

07/17/20

The contract is expected to be awarded at the July 21, 2020 council meeting, with work to start in August.