Skip to main content

2020 Sidewalk Rehabilitation Program

 

Project InformationData
Project # S-006-20
Category Sidewalks
Start Date May 2020
End Date May 2020
Percent Complete 100%
Village Contact Matthew Stern, Staff Engineer (630) 434-5463

Project Summary

This project provides for the rehabilitation of sections of sidewalk that have become vertically separated by saw cutting the lifted edge to provide a smooth walking surface.

Project Alerts

 

Recent Progress

06/05/20

2020 Sidewalk Rehabilitation Program is complete. Approximately 1460 vertical discontinuities were repaired this year all across the Village.

05/01/20

The contractor is scheduled to start work next week. Work will entail the saw cutting of lifted sidewalk edges to create a smoother walking surface.