2020 Finley Road at Finley Mall Traffic Signal Modernization

 

Table #: Project completion and contact information.
Project InformationData
Project # TR-024
Category Traffic  
Start Date March 2020
End Date September 2020
Project Status

               
            Project is Complete          

Village Contact

Will Lorton, Traffic Engineer (630) 434-6863

Project Summary

This project is the traffic signal modernization of Finley Road at Finley Square Mall. The project will completely replace the existing signal and improve pedestrian and vehicle accommodations.

Project Alerts

 

Recent Progress

5/22/20

Construction and installation of mast arms have been completed. Temporary signals and poles have been removed. Minor punch list items remain.

4/3/20

Sidewalk work was completed for the west leg of the intersection. Mobilization of the subcontractor out of the area should be completed by the end of this week. Site work is completed until mast arms and other materials are deliveried.

3/27/20

Work continued on the east side of the intersection with foundation forms placed, poured, and removed. All underground work should be completed by the end of the day today. Sidewalk work is scheduled to begin the week of 3/30/20.

2/28/20

Signs Placed for construction to begin 3/2/2020

9/20/19

Project is currently accepting bids for work.