2020 Fall Roadway Patching

 

Table #: Project completion and contact information.
Project InformationData
Project # ST-004D
Category Streets 
Start Date September 2020
End Date October 2020
Project Status

            Complete                            

Village Contact

Stephanie Graves, Staff Engineer (630) 434-5487

Project Summary

 

 

Project Alerts

 

 

 

Recent Progress

10/23/20

Project is complete.

10/16/20

Patching work was completed on Wednesday, 10/14.

10/09/20

The contractor started work on Thursday, October 8th, beginning on the north side of town and working their way south. There will be no work on Monday, October 12th, but the crew will be back on Tuesday, October 13th to finish the remaining patching locations.

10/2/20

The contractor is planning to be in town to start work on Thursday, October 8th. Areas of patching will see "Road Construction Ahead" signs and no parking signs staked in the parkway on Monday, October 5th.

9/18/20

Work is tentatively scheduled to begin the week of October 12th.

9/11/20

A preconstruction meeting is tentatively scheduled for Tuesday, September 15th.

9/4/20

The contract was approved at the September 1st Council meeting. A preconstruction meeting will be planned for the week of September 21st.

8/21/20

The contract will be presented to Council at the September 1, 2020 Council meeting.

8/14/20

The contract will be presented to Council at the September 1, 2020 Council meeting.

8/7/20

Bids were opened August 6, 2020 and are under review.

7/31/20

This project was advertised on July 23rd and bids will be opened on August 6th.

7/24/20

This project was advertised on July 23, 2020. Bids will be opened on August 6th.