Table #: Project completion and contact information.
Project InformationData
Project # SW-080-17B
Category Drainage
Start Date  
End Date
Project Status

               Suspended
                                                                           


Village Contact

Katherine Zirbel, Staff Engineer II (630) 434-5488

Project Summary

This project involves storm sewer improvements on the highlighted streets indicated below. Please click this link to view the Village's Construction Project Interactive Map:

 


The project includes installing storm sewers, constructing a detention pond on the east side of Belle Aire Lane where Virginia Street ends, as well as patching of the existing roadway where the new storm sewer will be installed. Also included are sidewalk improvements at some intersections, and resurfacing several roads.  

Project Alerts

This project has been suspended as part of the Village's COVID-19 Pandemic Financial Response Plan. The suspension of certain capital projects will continue until reliable funding sources are in place to support their completion.


The plan was presented at the April 7, 2020 Council meeting and can be viewed here:
COVID-19 Pandemic Financial Response plan

 

Recent Progress

3/13/20

Council has approved the award of the construction contract to Campanella & Sons.

2/21/20

Contractor bids have been received. The lowest responsible bid will be presented to Council March 3, 2020.

01/31/20

The project is out for bid and bids will be opened on February 14, 2020. Construction is expected to begin in April.