2019 Road Maintenance Resurfacing

 

Table #: Project completion and contact information.
Project InformationData
Project # ST-004
Category Streets 
Start Date June 2019
End Date October 2019
Project Status

               Green
(Project is on schedule.)       

Village Contact

Stephanie Graves, Staff Engineer (630) 434-5487

Project Summary

 

 StreetFrom StreetTo Street
61ST ST  BLODGETT AVE  GRAND AVE 
71ST ST DUNHAM RD OLD DUNHAM RD
75TH ST FRONTAGE FAIRVIEW AVE FLORENCE AVE
BENDING OAKS CT ELMORE AVE W. CUL DE SAC
BLODGETT AVE 55TH ST RANDALL ST
BLODGETT AVE 63RD ST 59TH ST
BURLINGTON AVE WALNUT AVE ROSE AVE
CURTISS ST WALNUT AVE KATRINE AVE
DOWNERS DR S. LIMIT JEFFERSON AVE
DUNHAM RD 71ST ST 67TH PL
ELM ST CHICAGO AVE OGDEN AVE
ELMORE AVE BELMONT RD LEE AVE
FAIRMOUNT AVE 55TH ST MAPLE AVE
GEORGE ST SPRINGSIDE AVE E END
JEFFERSON AVE SPRINGSIDE AVE PLYMOUTH ST
LEE AVE MAPLE AVE GILBERT AVE
LYMAN AVE 55TH ST MAPLE AVE
OXNARD DR WOODWARD AVE BOLSON DR
POWELL CT 71ST ST N END
RANDALL ST WASHINGTON ST LYMAN AVE
RANDALL ST FAIRMOUNT AVE BLODGETT AVE
SECOND ST FAIRVIEW AVE CUMNOR RD
SHERMAN AVE MAPLE AVE S. LIMITS
SPRINGSIDE AVE JEFFERSON AVE MAPLE AVE
STONEWALL AVE CONCORD DR BOLSON DR
WASHINGTON ST SUMMIT ST MAPLE AVE
WILLIAMS ST PLAINFIELD RD 75TH ST

 

Project Alerts

 

Recent Progress

5/24/19

The contract was approved on the May 21st Council Agenda. A pre-construction meeting will be scheduled in the coming weeks.

5/17/19

The contract will be on the May 21st Council Agenda for approval. Work is expected to start late June.

5/10/19

Bids were opened and read on May 3rd. The contract will be going to council May 14th and May 21st for approval. Construction is expected to begin in late June.

4/19/19

The 2019 Resurfacing Program is being advertised on April 19, 2019 and bids will be opened and read on May 3rd, 2019. Construction is expected to begin in late June/early July.