2019 Road Maintenance Resurfacing

 

Table #: Project completion and contact information.
Project InformationData
Project # ST-004
Category Streets 
Start Date June 2019
End Date October 2019
Project Status

               Green
(Project is on schedule.)       

Village Contact

Stephanie Graves, Staff Engineer (630) 434-5487

Project Summary

 

 StreetFrom StreetTo Street
61ST ST  BLODGETT AVE  GRAND AVE 
71ST ST DUNHAM RD OLD DUNHAM RD
75TH ST FRONTAGE FAIRVIEW AVE FLORENCE AVE
BENDING OAKS CT ELMORE AVE W. CUL DE SAC
BLODGETT AVE 55TH ST RANDALL ST
BLODGETT AVE 63RD ST 59TH ST
BURLINGTON AVE WALNUT AVE ROSE AVE
CURTISS ST WALNUT AVE KATRINE AVE
DOWNERS DR S. LIMIT JEFFERSON AVE
DUNHAM RD 71ST ST 67TH PL
ELM ST CHICAGO AVE OGDEN AVE
ELMORE AVE BELMONT RD LEE AVE
FAIRMOUNT AVE 55TH ST MAPLE AVE
GEORGE ST SPRINGSIDE AVE E END
JEFFERSON AVE SPRINGSIDE AVE PLYMOUTH ST
LEE AVE MAPLE AVE GILBERT AVE
LYMAN AVE 55TH ST MAPLE AVE
OXNARD DR WOODWARD AVE BOLSON DR
POWELL CT 71ST ST N END
RANDALL ST WASHINGTON ST LYMAN AVE
RANDALL ST FAIRMOUNT AVE BLODGETT AVE
SECOND ST FAIRVIEW AVE CUMNOR RD
SHERMAN AVE MAPLE AVE S. LIMITS
SPRINGSIDE AVE JEFFERSON AVE MAPLE AVE
STONEWALL AVE CONCORD DR BOLSON DR
WASHINGTON ST SUMMIT ST MAPLE AVE
WILLIAMS ST PLAINFIELD RD 75TH ST

 

Project Alerts

 

Recent Progress

9/20/19

This week, grinding continued on Burlington, Curtiss, Elmore, Bending Oaks Ct, and Lee.

Friday 9/20/19, paving is planned for Springside, George, Jefferson, Fairmount, Lyman, Washington, and Randall.

Saturday, level binder is planned for Second, Elm and Curtiss.

Monday, patching will take place on needed streets. Depending on the amount of patching areas, level binder is tentatively scheduled on Lee, Elmore, and Bending Oaks Ct for Wednesday 9/25/19. Patching will also take place on streets that require it.

Asphalt driveways are expected to be repaired next week or the following week. As temperatures fall below 80 degrees, the landscapers will resume work restoring disturbed areas. Grinding is also expected to be completed by 9/27/19, with Dunham, 71st, Powell Ct, Oxnard, and Stonewall.

9/13/19

Due to chances of rain this week, the contractor was unable to pave the locations they were hoping to complete.

Concrete was poured on Dunham, Oxnard, and Stonewall, and Elm and Second St were milled. Cleanup and prep took place on the streets to be paved.

Next week, all concrete work should be complete and the contractor will focus on paving all streets that have been milled, weather pending, and landscapers will continue restoration throughout town. An asphalt driveway crew will be in town within the next week or two to address the HMA driveways in need of repair.

9/6/19

This week, the contractor removed concrete curb, sidewalk, and driveway aprons on Oxnard and Stonewall, as well as spot locations on previously completed streets. The contractor poured concrete curb and sidewalk on Dunham Rd, 71st St, Powell Ct, and Curtiss.

Next week, the contractor will pour concrete curb, sidewalk, and driveway aprons on Oxnard and Stonewall, and will complete concrete removals on those same streets. Due to an unexpected delay, the contractor was not able to perform any asphalt grinding or paving work this week. Next week, the contractor is expected to be back in town to pave surface asphalt on Springside, Jefferson, George, and Downers. Level binder will be paved on Lyman, Fairmount, Washington, and Randall from Washington to Lyman. Grinding will continue on Second, Elm, Lee, Elmore, and Bending Oaks Ct.

The landscaper will start placing sod in restoration locations when temperatures are within specifications.

8/30/19

This week, surface asphalt was paved on Williams and leveling binder was paved on Springside and Jefferson. Concrete work continued on Bending Oaks Court and Curtiss, and concrete curb, sidewalk, and driveways were removed on Dunham Rd, 71st St, and Powell Court. Road milling continued on Fairmount, Lyman, Washington, and Randall, and is expected to continue on Second St, Elm, Elmore, Bending Oaks Ct, and Lee the week of 9/2.

Concrete curb, driveway, and sidewalk removals will take place on Curtiss, Oxnard (south side of the street), and Stonewall (east side of the street) next week Tuesday, and concrete will be poured on Wednesday, Thursday, and Friday. Dunham Rd, 71st St, and Powell Court will have concrete curb and sidewalk poured on Tuesday and Wednesday as well. Milled roads will be evaluated for patching early next week.

8/23/19

This week, concrete curb, sidewalk, and aprons were poured on Lyman, Washington, Randall (from Washington to Lyman), and Second. Curb was poured on Elmore and Springside, and sidewalk was partially poured on Springside and Elmore. Surface asphalt paving was completed on 61st St, Blodgett from 59th to 63rd, and Frontage Rd.

The contractor is expected to repair asphalt driveways on Second St, Fairmount, Washington, Frontage, Williams, and Randall (from Blodgett to Fairmount) on Saturday, 8/24. The underground contractor also came to town to lower in-pavement structures in anticipation of road work on Elm, Lee, and Elmore. The landscapre began prepping areas for restoration on Blodgett (from Randall to 55th) and Randall (from Blodgett to Fairmount). Concrete removals are expected to take place on Bending Oaks Ct and Curtiss (from Walnut to Katrine) on Saturday, 8/24.

Next week, road milling is expected to take place on Fairmount, Lyman, Washington, and Randall (from Washington to Lyman). Concrete curb, apron, and sidewalk will be poured on Elmore, Lee, Springside, Bending Oaks Ct, Elm, and Curtiss. Williams is expected to be paved with final asphalt surface. Concrete curb, sidewalk, and driveway apron removals are expected to take place on Monday or Tuesday, 8/26 or 8/27, schedule pending, with the concrete poured later in the week.

8/16/19

This week, concrete curb, sidewalk, and driveway aprons were removed on Second St, Lyman Ave, Randall St (Washington to Lyman), and Washington St. Concrete curb was poured on Second St and underground utilities were adjusted as well. Leveling binder was paved on Williams, Frontage Rd, Blodgett from 63rd to 59th, and Blodgett from 55th to Randall. Springside, Jefferson, and George were milled.

Friday 8/16, asphalt driveways will be replaced on both Blodgett streets, Williams, and Frontage Road. Saturday, 8/17, surface asphalt will be paved on both Blodgetts, 61st St, and Randall from Fairmount to Blodgett. Next week, concrete work will finish on Lyman, Washington, and Randall and is expected to continue to Elmore, Lee, and Bending Oaks Ct. Surface paving is expected to be placed on Williams and Frontage Rd.

8/2/19

This week, the asphalt surface of the roads were milled on Williams, Frontage Rd, and Blodgett from 59th to 62nd. In addition, concrete was poured on Blodgett Ave from 55th to Randall. Saturday, August 3rd, the contractor is planning on pouring the curb on Randall, between Blodgett and Fairmount, as well as completing the road patching on Williams, Frontage Rd, and Blodgett from 59th to 62nd. Concrete removals are expected to continue the week of 8/5/19 on Fairmount Ave and Lyman Ave. Road grinding the week of 8/5/19 is expected to continue on Blodgett from 55th to Randall.

7/26/19

This week, concrete curb, sidewalk, and driveway aprons were poured on Williams, Frontage Rd, Blodgett (59th to 63rd) and Blodgett (55th to Randall). The road on Williams will be milled on Tuesday, 7/30/19. The weeks of 7/29 & 8/05, grinding, patching, and the first layer of asphalt will follow on Frontage Rd, Blodgett (59th to 63rd), Blodgett (55th to Randall), and tentatively Dunham and 71st St. Concrete removals are expected to continue at the end of next week on Fairmount and Randall. "No Parking" signs were inadvertently posted in areas of the project that have not yet been notified of work. Letters have been mailed to the affected residents to provide additional information of the upcoming work.

7/19/19

Saw cutting work continued on Dunham Rd, Oxnard Ave, Stonewall Ave, Blodgett (from 59th to 63rd), and Second Street. Concrete removals began on Williams on 7/16, and on the 75th St Frontage Rd on 7/16. Concrete will be poured on Williams on 7/18, 7/19, and 7/22. Concrete removals are expected to begin on the 75th St Frontage Rd and Blodgett (from 59th to 63rd) on Monday, 7/22. Residents whose driveway access will be affected will receive additional correspondence from the Village with alternative parking information and scheduling. Following concrete work on Blodgett, the streets where concrete will be removed next will be Dunham, 71st, Powell Ct, Oxnard, and Stonewall.

7/12/19

Saw cutting began this week on WIlliams St. south of 75th. The work will continue on the 75th St. Frontage Road and Dunham Rd. Next week, concrete removals are expected to begin in the areas that have been sawcut. Residents whose driveway access will be affected will receive additional correspondence from the Village with alternative parking information and scheduling.

7/5/19

Saw cutting will begin July 9th in the streets located in the southern half of town. Concrete removals are expected to begin July 15th.

6/28/19

Work will start the week of July 8th on the streets located in the southern half of town. Residents who will be impacted first have been notified via mail. Curb and sidewalk are being marked out for replacement, and the first work operations will be sawcutting and curb/sidewalk removal.

6/21/19

A pre-construction meeting is scheduled for 6/21/19, and the schedule of work will be established at that time. Field markings will continue to take place as weather permits. Construction will begin Monday, July 8, 2019.

6/14/19

A pre-construction meeting will be held the week of 6/17/19, and a schedule of work will be established at that time. Removals and layout will continue to be marked in field as weather permits. Construction work will begin Monday, July 8, 2019.

6/7/19

A pre-construction meeting will be held the week of 6/17/19, and a schedule of work will be established at that time. Removals and layout will continue to be marked in the field.

5/31/19

Field markings have been started throughout the streets in this year's program to specify areas of removal/replacement in preparation for work. Notices will be sent to residents prior to start of work.

5/24/19

The contract was approved on the May 21st Council Agenda. A pre-construction meeting will be scheduled in the coming weeks.

5/17/19

The contract will be on the May 21st Council Agenda for approval. Work is expected to start late June.

5/10/19

Bids were opened and read on May 3rd. The contract will be going to council May 14th and May 21st for approval. Construction is expected to begin in late June.

4/19/19

The 2019 Resurfacing Program is being advertised on April 19, 2019 and bids will be opened and read on May 3rd, 2019. Construction is expected to begin in late June/early July.