Skip to main content

2019 Road Maintenance Resurfacing

 

Table #: Project completion and contact information.
Project InformationData
Project # ST-004
Category Streets 
Start Date June 2019
End Date October 2019
Project Status

               Green
(Project is on schedule.)       

Village Contact

Stephanie Graves, Staff Engineer (630) 434-5487

Project Summary

 

 StreetFrom StreetTo Street
61ST ST  BLODGETT AVE  GRAND AVE 
71ST ST DUNHAM RD OLD DUNHAM RD
75TH ST FRONTAGE FAIRVIEW AVE FLORENCE AVE
BENDING OAKS CT ELMORE AVE W. CUL DE SAC
BLODGETT AVE 55TH ST RANDALL ST
BLODGETT AVE 63RD ST 59TH ST
BURLINGTON AVE WALNUT AVE ROSE AVE
CURTISS ST WALNUT AVE KATRINE AVE
DOWNERS DR S. LIMIT JEFFERSON AVE
DUNHAM RD 71ST ST 67TH PL
ELM ST CHICAGO AVE OGDEN AVE
ELMORE AVE BELMONT RD LEE AVE
FAIRMOUNT AVE 55TH ST MAPLE AVE
GEORGE ST SPRINGSIDE AVE E END
JEFFERSON AVE SPRINGSIDE AVE PLYMOUTH ST
LEE AVE MAPLE AVE GILBERT AVE
LYMAN AVE 55TH ST MAPLE AVE
OXNARD DR WOODWARD AVE BOLSON DR
POWELL CT 71ST ST N END
RANDALL ST WASHINGTON ST LYMAN AVE
RANDALL ST FAIRMOUNT AVE BLODGETT AVE
SECOND ST FAIRVIEW AVE CUMNOR RD
SHERMAN AVE MAPLE AVE S. LIMITS
SPRINGSIDE AVE JEFFERSON AVE MAPLE AVE
STONEWALL AVE CONCORD DR BOLSON DR
WASHINGTON ST SUMMIT ST MAPLE AVE
WILLIAMS ST PLAINFIELD RD 75TH ST

 

Project Alerts

 

Recent Progress

7/19/19

Saw cutting work continued on Dunham Rd, Oxnard Ave, Stonewall Ave, Blodgett (from 59th to 63rd), and Second Street. Concrete removals began on Williams on 7/16, and on the 75th St Frontage Rd on 7/16. Concrete will be poured on Williams on 7/18, 7/19, and 7/22. Concrete removals are expected to begin on the 75th St Frontage Rd and Blodgett (from 59th to 63rd) on Monday, 7/22. Residents whose driveway access will be affected will receive additional correspondence from the Village with alternative parking information and scheduling. Following concrete work on Blodgett, the streets where concrete will be removed next will be Dunham, 71st, Powell Ct, Oxnard, and Stonewall.

7/12/19

Saw cutting began this week on WIlliams St. south of 75th. The work will continue on the 75th St. Frontage Road and Dunham Rd. Next week, concrete removals are expected to begin in the areas that have been sawcut. Residents whose driveway access will be affected will receive additional correspondence from the Village with alternative parking information and scheduling.

7/5/19

Saw cutting will begin July 9th in the streets located in the southern half of town. Concrete removals are expected to begin July 15th.

6/28/19

Work will start the week of July 8th on the streets located in the southern half of town. Residents who will be impacted first have been notified via mail. Curb and sidewalk are being marked out for replacement, and the first work operations will be sawcutting and curb/sidewalk removal.

6/21/19

A pre-construction meeting is scheduled for 6/21/19, and the schedule of work will be established at that time. Field markings will continue to take place as weather permits. Construction will begin Monday, July 8, 2019.

6/14/19

A pre-construction meeting will be held the week of 6/17/19, and a schedule of work will be established at that time. Removals and layout will continue to be marked in field as weather permits. Construction work will begin Monday, July 8, 2019.

6/7/19

A pre-construction meeting will be held the week of 6/17/19, and a schedule of work will be established at that time. Removals and layout will continue to be marked in the field.

5/31/19

Field markings have been started throughout the streets in this year's program to specify areas of removal/replacement in preparation for work. Notices will be sent to residents prior to start of work.

5/24/19

The contract was approved on the May 21st Council Agenda. A pre-construction meeting will be scheduled in the coming weeks.

5/17/19

The contract will be on the May 21st Council Agenda for approval. Work is expected to start late June.

5/10/19

Bids were opened and read on May 3rd. The contract will be going to council May 14th and May 21st for approval. Construction is expected to begin in late June.

4/19/19

The 2019 Resurfacing Program is being advertised on April 19, 2019 and bids will be opened and read on May 3rd, 2019. Construction is expected to begin in late June/early July.