2019 Road Maintenance Rejuvenation

 

Table #: Project completion and contact information.
Project InformationData
Project # ST-004E
Category Streets 
Start Date June 2019
End Date October 2019
Project Status

               Green
(Project is on schedule.)       

Village Contact

Stephanie Graves, Staff Engineer (630) 434-5487

Project Summary

Work is part of the on-going annual maintenance of the Village's 166 miles of streets. This project covers streets that were repaved last year. Streets generally remain open to traffic during most of this activity.

 

Project Alerts

 

 

Recent Progress

9/6/19

The contractor completed work in town this week and the project is complete.

8/30/19

The contractor will continue work in town through early next week (week of 9/2). The process for work is: Spraying the road with reclamite and sanding immediately after. The following day, the street sweeper comes in to clean up. Work is expected to wrap up with spraying on Tuesday, 9/3 and sweeping Wednesday, 9/4.

8/16/19

Contract was awarded on 8/6/19, and work is expected to begin 8/27/19, weather pending.

7/19/19

Bids were opened on 7/2/19 and will be presented to Council on August 6th.

7/12/19

Bids were opened on 7/2/19 and will be presented to Council on August 6th.

7/5/19

Bids were opened on 7/2/19, and will be presented to Council on August 6th.

6/28/19

Bids were advertised on 6/18/19, and will be opened on 7/2/19. Work will start late summer.

6/21/19

Bids were advertised 6/18/19 and will be opened 7/2/19. Work will start late summer.