2019 Road Maintenance Crack Sealing

 

Table #: Project completion and contact information.
Project InformationData
Project # ST-004C
Category Streets 
Start Date June 2019
End Date October 2019
Project Status

               Green
(Project is on schedule.)       

Village Contact

Stephanie Graves, Staff Engineer (630) 434-5487

Project Summary

Work is part of the on-going annual maintenance of the Village's 166 miles of streets. This project covers streets that were resurfaced within the past 2-3 years. Streets generally remain open to traffic during most of this activity.

 

Project Alerts

5/17/19

This project was awarded by Council April 9, 2019. Schedule of work will be determined in June.

 

 

Recent Progress

7/19/19

The rubber crack filling application was completed on July 17th. The remaining work is for fiber crack filling application, and the schedule is pending for their return and completion.

7/12/19

The contractor is continuing work throughout town. Work is expected to be completed in the week of July 15th.

7/5/19

The contractor is continuing work throughout town. Red and white signs are in the parkway to alert of work on impacted streets. Commuter Parking Lot H will be receiving this treatment but is expected to remain open.

6/28/19

The contractor has mobilized in town as of 6/27/19, and has several crews in town at various locations. Impacted residents are being notified in advance of work by the contractor. Commuter Parking Lot H is also included in the list of locations that will receive this treatment in the coming weeks.

6/21/19

Rain is impeding the contractor's ability to perform work. An approximate schedule will be established in the coming weeks.

6/14/19

Rain is impeding the contractor's ability to perform work. An approximate schedule will be established in the coming weeks.

6/7/19
A pre-construction meeting was held on 6/6/19, and the contractor will be providing an approximate schedule in the coming weeks.