2018 Road Maintenance Resurfacing (Contract B)

 

Table #: Project completion and contact information.
Project InformationData
Project # ST-004
Category Streets 
Start Date June, 2018
End Date October, 2018
Project Status

               Green
(Project is on schedule.)       

Village Contact

Scott Barr, Staff Engineer (630) 434-5488

Project Summary

Work is part of the on-going annual maintenance of the Village's 166 miles of streets. This project covers approximately 7 miles of roadway and shall include pavement removal and replacement, repairs to existing curb and gutter / sidewalk ramps, surface milling and repaving and all related restoration. Streets generally remain open to traffic during most of this activity.

 

 

Project typically progresses through the designated areas of the Village in phases / types of work; Although variable, common staging may include concrete work first with repair / replacement of existing curb and gutter where necessary; Some storm structure repair may be included at this point; Affected sidewalk ramps at intersections may be upgraded / added where necessary; Concrete aprons affected by the curb & gutter work are repaired; Affected / damaged asphalt aprons may be repaired now or later; Deteriorated pavement is milled off followed by base repair; Street is repaved with two layers of new asphalt; New stone shoulders are replaced / reestablished along new pavement without curb & gutter; Disturbed turf areas are restored with new sod.

 StreetFrom StreetTo Street
62nd Pl Brookbank Rd Carpenter St
67th Ct Fairview Ave West End 
68th St Fairmount Ave Fairview Ave
72nd Ct East Cul De Sac 72nd St
73rd St Hartford Rd Fairmount Ave
73rd St Baybury Rd East End
74th St Hartford Rd York Rd
Ashbury Ave Baybury Rd Canterbury Pl
Baybury Rd Ashbury Ave 73rd St
Bentley Ct Grand Ave 73rd St
Blackburn Pl N. Cul De Sac 68th St
Blanchard St Dunham Rd Main St
Brookbank Rd 55th St S. of Blanchard
Brookbank Rd 59th St 63rd St
Buckingham Pl Grand Ave Fairview Ave
Canterbury Pl N. Cul De Sac 75th St
Churchill Ct Buckingham Pl N. Cul De Sac
Claremont Dr Pinewood Dr Main St
Fairmount Ave 67th St 72nd St
Gilbert Ave Cornell Ave Carpenter St
Grand Ave Buckingham Pl 68th St
Hartford Rd 74th St 73rd St
Lyman Ave 55th St South of 59th St
Main St 75th St Lemont Rd
Middaugh Ave 59th St 55th St
Osage Ave S. Cul De Sac 68th St
Osage Pl N. Cul De Sac 68th St
Pinewood Dr Claremont Dr South End
Pinewood Dr Pinewood Dr N/S Lemont Rd
Ridgeview St W. Cul De Sac Fairmount Ave
Ridgeview St Fairmount Ave E. Cul De Sac
Stockley Rd W. of Canterbury 74th St
Trent Rd 74th St 73rd St
Wolf Pl S. Cul De Sac 68th St
York Rd 74th St 73rd St

 

Project Alerts

 

Recent Progress

11/9/2018

*A "Punch List" of items for contractor to repair / clean up etc has been generated. This work is ongoing.

11/2/2018

*Final parkway prep and sod placement complete throughout project. *A "Punch List" of items for contractor to repair / clean up etc has been generated. This work is ongoing.

10/26/2018

*Final parkway prep has been ongoing throughout remaining affected streets. Sod placement completed 72nd Ct, Ridgeview and majority of Fairmount. Final prep and sod placement may continue Fairmount / 68th St area 10/26, 10/27 and next week progressing to the north. *A "Punch List" of items for contractor to repair / clean up etc has been generated. This work is ongoing.

10/19/2018

*Final parkway prep has been ongoing in the Fairmount / 68th St area. This work along with sod placement may continue 10/20 and next week and should progress through the Fairmount / 68th St area and to the north. *A "Punch List" of items for contractor to repair / clean up etc has been generated. This work is ongoing.

10/12/2018

*Replacement of pavement striping has been completed throughout the project. *Final parkway prep and sod placement has been delayed due to weather. Parkway restoration work may continue late this week or early next and should progress through the Fairmount / 68th St area and to the north. *A "Punch List" of items for contractor to repair / clean up etc has been generated. This work is ongoing.

10/5/2018

*Final surface course paving completed on Gilbert Ave 9/28. *Placement of new stone shoulders completed in Blanchard / Middaugh area, Lyman Ave, west end Gilbert Ave, 67th Ct and 73rd St east of Baybury. *Final parkway prep and sod placement completed on Main St, the Pinewood area and majority of Baybury to York area. Parkway restoration work should progress into the Fairmount / 68th St area and to the north next week. *Replacement of pavement striping may begin next week weather permitting. *A "Punch List" of items for contractor to repair / clean up etc is being generated.

9/28/2018

*Base patching / repair operations completed on Brookbank south of 59th and Lyman south of 59th. *First course of new asphalt paving completed on last of of Brookbank and Lyman south of 59th St. *Final surface course paving completed on Brookbank (59th to 63rd) and Lyman south of 59th. Surface course paving scheduled to begin on Gilbert Ave 9/28. *Repair / replacement of damaged asphalt driveways completed on Brookbank south of Blanchard and south of 59th, Lyman south of 59th, Gilbert and 74th St.*Placement of new stone shoulders may begin next week in the Blanchard / Middaugh area. Final parkway prep and sod placement ongoing on Main St, the Pinewood area and Baybury to York area. Parkway restoration work should progress into the Fairmount / 68th St area and to the north next week.

9/21/2018

*Base patching / repair operations completed on Gilbert and majority complete on Brookbank (59th to 63rd) and Lyman south of 59th. Base repairs should be completed next week. *First course of new asphalt paving completed on Gilbert Ave and majority of Brookbank except for northbound lane (59th to 60th Pl) First course paving operations may continue next week followed by final surface course paving. *Adjustment of manhole frames in the pavement is scheduled to begin 9/21 on Brookbank and Gilbert. *Placement of new stone shoulders may begin next week in the Blanchard / Middaugh area. *Repair / replacement of damaged asphalt driveways may continue next week. Final parkway prep ahead of sod placement may begin next week in the south areas of the project and progress north.

9/14/2018

*Base patching operations should continue next week progressing to Brookbank (59th to 63rd), Lyman south of 59th and Gilbert Ave. Paving operations to follow base patching. *Placement of new stone shoulders may begin next week in the Blanchard / Middaugh area. *Repair / replacement of damaged asphalt driveways may continue next week. Final parkway prep ahead of sod placement may begin next week in the south areas og the project and progress north.

9/7/2018

*Base patching operations should continue next week progressing to Brookbank (59th to 63rd), Lyman south of 59th and Gilbert Ave. Paving operations to follow base patching. *Surface course paving now complete in the Grand / Buckingham area, 67th Ct, throughout the 73rd / York / Trent area, Baybury area, Pinewood / Claremont area, 62nd Pl and Brookbank south of Blanchard. *Placement of new stone shoulders may begin next week in the Blanchard / Middaugh area. *Preliminary parkway restoration prep is ongoing throughout the project at all locations disturbed by curb repairs etc. Final parkway prep and sod placement typically takes place when cooler weather is more common in September to October.

8/31/2018

*Surface removal / milling operations completed on Brookbank N of 63rd, 62nd Pl, Gilbert Ave and Lyman south of 59th St. *Base patching operations completed throughout the 73rd St / York area, Baybury area and Pinewood area. This work may continue next week and progress to Brookbank (59th to 63rd), Lyman south of 59th and Gilbert Ave. *Paving operations ongoing in the Fairmount / 68th St area with surface course completed on Fairmount, 68th St, Wolf, Osage Ave, Osage Pl, Blackburn Pl, Ridgeview and 72nd Ct. Paving operations scheduled to continue 8/31 with first course (Level Binder) paving through 73rd / York area, Baybury area and Pinewood area. Level and surface paving operations may continue next week. *Preliminary parkway restoration prep is ongoing throughout the project at all locations disturbed by curb repairs etc. Final parkway prep and sod placement typically takes place when cooler weather is more common in September to October.

8/24/2018

*Concrete repairs majority complete on Lyman south of 59th and Brookbank from 59th St to 63rd St. Remaining concrete repairs may be completed next week. *Surface removal / milling operations completed on Ashbury, Baybury, 73rd east of Baybury and the Pinewood area and ongoing on Brookbank north of 63ed St. Milling operations scheduled to continue on Brookbank N of 63rd, 62nd Pl, Gilbert Ave and progress to Lyman south of 59th 8/23. Remilling part of Brookbank south of Blanchard may also take place. *Base patching operations completed throughout the Fairmount / 68th St area, Ridgeview, 72nd Ct and ongoing in the 73rd St / York area. This work may continue next week and progress to other milled locations. *Paving operations ongoing in the Fairmount / 68th St area with first course (level binder) completed on Fairmount north of Claremont, 68th, Wolf, Osage Ave, 67th Ct, Grand, Bentley, Buckingham, and Churchill. Paving operations should continue in this area next week progressing to Fairmount south of Claremont etc. *Manhole frame adjustments in the pavement are scheduled to take place 8/25 on Fairmount north of Claremont and 68th St. *Preliminary parkway restoration prep is ongoing throughout the project at all locations disturbed by curb repairs etc. Final parkway prep and sod placement typically takes place when cooler weather is more common in September to October.

8/17/2018

Concrete repairs majority complete on Lyman south of 59th and Brookbank from 59th St to 63rd St. Remaining concrete repairs may be completed next week. Surface removal / milling operations may continue on Ashbury, Baybury, 73rd east of Baybury and the Pinewood area next week. This work may also progress to Lyman south of 59th and Gilbert Ave next week. Base patching operations scheduled to begin throughout the Fairmount / 68th St area next week and progress south to 72nd Ct and the 73rd St / York area and other milled locations. Surface course paving now complete on Middaugh north of Blanchard and Lyman (55th St to 59th St). Paving operations should begin in the Fairmount / 68th St area next week. Asphalt driveway repairs at El Sierra School should be completed next week. Preliminary parkway restoration prep is ongoing throughout the project at all locations disturbed by curb repairs etc. Final parkway prep and sod placement typically takes place when cooler weather is more common in September to October.

8/10/2018

Concrete repairs majority complete on Lyman south of 59th, Gilbert Ave and Brookbank south of 55th St and ongoing on Brookbank south of 59th St and 62nd Pl. Remaining concrete repairs may be completed next week. Surface removal / milling operations completed in the Fairmount / 68th St area, 67th Ct, Ridgeview, 72nd Ct, the 73rd to Stockley area and Canterbury. This work may progress to Ashbury, Baybury, 73rd east of Baybury, the Pinewood area and Lyman south of 59th next week. Base patching operations to follow milling work may begin in the Fairmount area next week. Surface course paving now complete on Blanchard, Brookbank north of Blanchard and Middaugh south of Blanchard. Paving operations may continue in the Brookbank / Middaugh area and Lyman north of 59th St. next week.

 

8/3/2018

The majority of Concrete curb & gutter repair work complete in the Pinewood area, the Baybury to York Rd area, 72nd Ct and the Fairmount / 68th St area. This work to continue and should be completed in these areas next week. Concrete repairs should progress to Lyman south of 59th, Gilbert Ave and Brookbank south of 55th St and south of 59th St next week. Surface removal / milling operations should begin in the Fairmount / 68th St area next week and progress to the Pinewood area and Baybury to York area. Base patching operations will follow milling work. Paving operations complete Main St north of 75th St and ongoing in the Blanchard / Middaugh area and Lyman north of 59th St. Surface course paving may continue in these areas next week.

7/27/2018

Concrete curb & gutter repair work majority complete in the Pinewood area, the Baybury to York Rd area, 72nd Ct and the Fairmount / 68th St area. This work to continue and may be completed in these areas next week. Concrete repairs may progress to Lyman south of 59th, Gilbert Ave and Brookbank south of 55th St and south of 59th St next week. Surface removal / milling operations may begin in the Pinewood area and Baybury area sometime next week. Base patching operations completed on Main St, Middaugh / Blanchard area and Lyman north of 59th St. Paving operations to begin on Main St and the Blanchard area 7/27 and should continue next week through Lyman north of 59th St.

7/20/2018

Concrete curb & gutter repair work ongoing in the Pinewood & Old Main St area, the Baybury to York Rd area, 72nd Ct and the Fairmount / 68th St area. This work to continue and may be completed in these areas next week. Concrete repairs may progress to Lyman south of 59th, Gilbert Ave and Brookbank south of 55th. Surface removal / milling operations completed on Middaugh, Blanchard, Brookbank south of 55th and Lyman north of 59th. Milling operations may begin in the Pinewood area and Baybury area sometime next week. Base patching operations may begin on Main St, Middaugh area and Lyman next week.

7/13/2018

Concrete curb & gutter repair work ongoing in the Pinewood & Old Main St area, the Baybury to York Rd area, 72nd Ct and the Fairmount / 68th St. This work to continue and may be completed in these areas next week. Surface removal / milling operations completed on Main St and may begin in the Pinewood area and Baybury area sometime next week. Base patching operations may begin on Main St next week.

7/6/2018

Road Construction signage placed throughout the south 67th St to 75th St areas. Concrete curb & gutter repair work ongoing in the Pinewood & Old Main St area as well as the Baybury to York Rd area. This work should continue and progress to 72nd Ct and the Fairmount / 68th St area on Friday, July 6 and into next week. Surface removal / milling operations may begin on Main St sometime next week.

6/22/2018

Road construction signage may begin to be placed next week in the 67th St to 75th St areas.  Concrete curb and gutter repair work may also begin in the south areas near 75th St.