Skip to main content

2018 New Sidewalk

Project InformationData
Project #  S-010
Category Sidewalks
Start Date July, 2018
End Date

October, 2018

Project Status

 

             Yellow
(Project is delayed due to weather.)


Village Contact

 

Matthew Stern, Staff Engineer (630) 434-5463

 

Project Summary

 

This project includes the installation of new sidewalk on the east side of Drendel Rd from Odgen Ave to Indianapolis Ave and on the east side of Cross St from Haddow Ave to Burlington Ave.

 

2018 New Sidewalk Project: Map

 

Recent Progress

12/14/2018
Parkway restoration is underway. Due to limited availability of sod, seed and blanket is being used.

11/9/2018
Drainage work is complete. Staff is working with contractor to complete sod restoration as soon as possible.

11/2/2018
Drainage work is complete. Staff is working with contractor to complete sod restoration as soon as possible.

10/26/2018
Sod restoration has been delayed due to weather and unexpected, outstanding drainage work, which is expected to be done by the end of this week. Sod restoration will follow completion of the drainage work.

10/12/2018
Sod placement has been delayed due to weather. Sod is expected to be placed next week, weather pending.

10/5/2018
Contractor has begun preparing parkways for sod placement. Sod is expected to be placed next week.

9/28/2018
Contractor has begun preparing parkways for sod placement. Sod is expected to be placed next week.

9/21/2018
Contractor has begun preparing parkways for sod placement. Sod is expected to be placed next week.

9/14/2018
Contractor is expected to begin sod placement next week.

9/7/2018
Placement of sod has been delayed due to warm weather and rain; expected to take place within the next couple weeks, weather pending.

8/24/2018
Placement of sod has been delayed due to warm weather; expected to take place within the next couple weeks, weather pending.

8/10/2018
Contractor completed driveway replacement and road patching and reshaping of ditches on both Cross St and Drendel Rd. Contractor has completed majority of topsoil placement for sod restoration. Placement of sod is expected next week, weather permitting.

8/3/2018
This week
Contractor completed installation of sidewalk on Cross St and sidewalk, curb and gutter on Drendel Rd.
Next week
Restoration of street pavement, driveways and turf grass is expected to continue.

7/27/2018
This week
Contractor completed installation of sidewalk on Cross St and sidewalk, curb and gutter on Drendel Road.
Next week
Restoration of street pavement, driveways and turf grass is underway and expected to continue next week.

7/13/2018
Contractor has begun tree and shrub removal. Work is expected to continue into the week of July 16. 

7/6/2018
Contractor is expected to mobilize and begin work the week of July 9.

6/29/2018
The contractor is expected to mobilize the week of July 2. Removals and potential driveway impacts will start after Independence Day holiday on July 4.